Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
322
matching recommendationsNAICS | 33312 | Construction Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0165 # 03 Y:2021 | 03 | 2021 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,846 | $0 | Not Implemented |
WM0165 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,709 | $7,202 | Not Implemented |
WM0165 # 01 Y:2021 | 01 | 2021 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $23,243 | $76,150 | Not Implemented |
BS0151 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,055 | $2,536 | Not Implemented |
BS0151 # 02 Y:2021 | 02 | 2021 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $893 | $710 | Not Implemented |
BS0151 # 03 Y:2021 | 03 | 2021 | INSULATE BARE EQUIPMENT | $8,310 | $527 | Not Implemented |
BS0151 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $272 | $522 | Not Implemented |
BS0150 # 01 Y:2021 | 01 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $937 | $22 | Not Implemented |
BS0150 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $629 | $375 | Not Implemented |
BS0150 # 03 Y:2021 | 03 | 2021 | INSTALL OCCUPANCY SENSORS | $151 | $180 | Not Implemented |
BS0150 # 04 Y:2021 | 04 | 2021 | INSTALL SKYLIGHTS | $254 | $2,020 | Not Implemented |
BS0150 # 05 Y:2021 | 05 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $682 | $1,180 | Not Implemented |
AM0804 # 02 Y:2020 | 02 | 2020 | OPTIMIZE PLANT POWER FACTOR | $11,260 | $16,200 | Not Implemented |
AM0804 # 01 Y:2020 | 01 | 2020 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $124,900 | $15,000 | Not Implemented |
AM0804 # 03 Y:2020 | 03 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,800 | $0 | Not Implemented |
AM0804 # 04 Y:2020 | 04 | 2020 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $630 | $100 | Implemented |
AM0804 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $505 | $13 | Implemented |
OK1014 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,017 | $1,750 | Implemented |
OK1014 # 02 Y:2019 | 02 | 2019 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,114 | $3,878 | Implemented |
OK1014 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,926 | $9,064 | Implemented |
OK1010 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,016 | $11,730 | Not Implemented |
OK1010 # 06 Y:2019 | 06 | 2019 | USE OPTIMUM THICKNESS INSULATION | $11,922 | $53,750 | Not Implemented |
OK1010 # 05 Y:2019 | 05 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,024 | $3,948 | Not Implemented |
OK1010 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $885 | $1,760 | Implemented |
OK1010 # 03 Y:2019 | 03 | 2019 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,032 | $947 | Implemented |