Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
548
matching recommendationsNAICS | 33361 | Engine, Turbine, and Power Transmission Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2201 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,036 | $48,285 | Implemented |
UC2201 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,728 | $2,000 | Implemented |
UC2201 # 05 Y:2022 | 05 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,009 | $4,000 | Not Implemented |
UC2201 # 06 Y:2022 | 06 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,185 | $200 | Not Implemented |
UC2201 # 07 Y:2022 | 07 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $158,531 | $626,592 | Not Implemented |
UC2201 # 08 Y:2022 | 08 | 2022 | PAY UTILITY BILLS ON TIME | $530 | $0 | Implemented |
UC2201 # 09 Y:2022 | 09 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,563 | $0 | Implemented |
AM0851 # 02 Y:2022 | 02 | 2022 | OPTIMIZE PLANT POWER FACTOR | $7,294 | $18,267 | Not Implemented |
AM0851 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $42,809 | $2,862 | Not Implemented |
AM0851 # 03 Y:2022 | 03 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $277 | $972 | Implemented |
AM0851 # 04 Y:2022 | 04 | 2022 | USE SYNTHETIC LUBRICANT | $185 | $300 | Implemented |
AM0851 # 05 Y:2022 | 05 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $650 | $1,795 | Not Implemented |
AM0851 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $348 | $750 | Not Implemented |
AM0851 # 07 Y:2022 | 07 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $580 | $40 | Not Implemented |
AM0851 # 08 Y:2022 | 08 | 2022 | USE PHOTOCELL CONTROLS | $120 | $261 | Not Implemented |
TT0279 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,432 | $4,000 | Not Implemented |
TT0279 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,957 | $250 | Not Implemented |
TT0279 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,514 | $12,000 | Not Implemented |
TT0279 # 02 Y:2022 | 02 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $12,173 | $63,875 | Not Implemented |
TT0279 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $43,670 | $43,750 | Implemented |
IC0265 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,567 | $5,100 | Implemented |
IC0265 # 02 Y:2022 | 02 | 2022 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $705 | $304 | Implemented |
IC0265 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,312 | $7,533 | Implemented |
IC0265 # 04 Y:2022 | 04 | 2022 | ELIMINATE COMBUSTIBLE GAS IN FLUE GAS | $19,650 | $2,435 | Not Implemented |
OK1073 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,548 | $12,334 | Not Implemented |