IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

299

matching recommendations
Reset
NAICS 333911 Pump and Pumping Equipment Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0409 # 06 Y:2012 06 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $793 $500 Not Implemented
BD0409 # 07 Y:2012 07 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $535 $450 Implemented
BD0409 # 08 Y:2012 08 2012 USE PHOTOCELL CONTROLS $307 $200 Implemented
BD0409 # 09 Y:2012 09 2012 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $1,782 $1,500 Not Implemented
BD0409 # 10 Y:2012 10 2012 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $1,032 $1,600 Not Implemented
BD0409 # 11 Y:2012 11 2012 USE EVAPORATION TO CONCENTRATE MATERIAL $153 $600 Not Implemented
IA0465 # 01 Y:2011 01 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,456 $246 Not Implemented
IA0465 # 02 Y:2011 02 2011 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,745 $396 Not Implemented
IA0465 # 03 Y:2011 03 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,614 $7,406 Not Implemented
IA0465 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $27,910 $60,314 Not Implemented
IA0465 # 05 Y:2011 05 2011 INSTALL OCCUPANCY SENSORS $1,368 $616 Not Implemented
IA0465 # 06 Y:2011 06 2011 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $302 $13 Not Implemented
IA0465 # 07 Y:2011 07 2011 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,240 $8,646 Not Implemented
IA0465 # 08 Y:2011 08 2011 USE RADIANT HEATER FOR SPOT HEATING $20,214 $48,000 Not Implemented
OK0812 # 01 Y:2011 01 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $34,390 $92,072 Implemented
OK0812 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,843 $750 Implemented
OK0812 # 03 Y:2011 03 2011 INSTALL OCCUPANCY SENSORS $11,401 $77,770 Not Implemented
OK0812 # 04 Y:2011 04 2011 INSTALL OCCUPANCY SENSORS $6,323 $26,111 Implemented
OK0812 # 05 Y:2011 05 2011 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $13,390 $7,255 Not Implemented
OK0812 # 06 Y:2011 06 2011 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $12,936 $21,477 Not Implemented
OK0812 # 07 Y:2011 07 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,301 $7,605 Not Implemented
OK0812 # 08 Y:2011 08 2011 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $2,925 $14,300 Implemented
OK0812 # 09 Y:2011 09 2011 INSTALL TIMERS AND/OR THERMOSTATS $801 $353 Implemented
OK0812 # 10 Y:2011 10 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,148 $7,130 Not Implemented
TT0059 # 01 Y:2011 01 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $18,600 $38,200 Implemented