Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
300
matching recommendationsNAICS | 334418 | Printed Circuit Assembly (Electronic Assembly) Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MU0056 # 05 Y:2024 | 05 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $120 | $187 | n/a |
MU0056 # 07 Y:2024 | 07 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,248 | $158,400 | n/a |
MU0056 # 02 Y:2024 | 02 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $601 | $1,181 | n/a |
MU0056 # 06 Y:2024 | 06 | 2024 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,122 | $0 | n/a |
MU0056 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8 | $0 | n/a |
MU0056 # 01 Y:2024 | 01 | 2024 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $42,634 | $3,703 | n/a |
MU0056 # 04 Y:2024 | 04 | 2024 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $502 | $207 | n/a |
UF0619 # 02 Y:2024 | 02 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $11,318 | $25,440 | n/a |
UF0619 # 07 Y:2024 | 07 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,007 | $0 | n/a |
UF0619 # 09 Y:2024 | 09 | 2024 | AUTOMATE FINISHING PROCESS | $315,000 | $181,056 | n/a |
UF0619 # 01 Y:2024 | 01 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $16,482 | $6,000 | n/a |
UF0619 # 06 Y:2024 | 06 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,257 | $5,940 | n/a |
UF0619 # 10 Y:2024 | 10 | 2024 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $300,000 | $183,056 | n/a |
UF0619 # 08 Y:2024 | 08 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $705 | $1,252 | n/a |
UF0619 # 05 Y:2024 | 05 | 2024 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $3,458 | $9,470 | n/a |
UF0619 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,989 | $36,000 | n/a |
UF0619 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,655 | $13,445 | n/a |
AS0569 # 07 Y:2023 | 07 | 2023 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $229 | $86 | n/a |
AS0569 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,444 | $7,395 | n/a |
AS0569 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30,436 | $18,656 | n/a |
AS0569 # 04 Y:2023 | 04 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,945 | $490 | n/a |
AS0569 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $327 | $146 | n/a |
AS0569 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,653 | $5,151 | n/a |
AS0569 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $5,717 | $3,715 | n/a |
IP0186 # 06 Y:2023 | 06 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,614 | $2,164 | n/a |