Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsNAICS | 33451 | Navigational, Measuring, Electromedical, and Control Instruments Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0573 # 01 Y:2016 | 01 | 2016 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $2,610 | $100 | Not Implemented |
NC0573 # 06 Y:2016 | 06 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $418 | $75 | Not Implemented |
NC0573 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,685 | $13,453 | Implemented |
NC0573 # 07 Y:2016 | 07 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $618 | $160 | Not Implemented |
NC0573 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,606 | $76,556 | Implemented |
NC0573 # 04 Y:2016 | 04 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $105 | $200 | Implemented |
NC0573 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $219 | $100 | Implemented |
NC0475 # 05 Y:2013 | 05 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,988 | $4,750 | Not Implemented |
NC0475 # 04 Y:2013 | 04 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $620 | $100 | Not Implemented |
NC0475 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $975 | $1,124 | Not Implemented |
NC0475 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $9,597 | $5,600 | Not Implemented |
NC0475 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,801 | $48,075 | Not Implemented |
NC0475 # 06 Y:2013 | 06 | 2013 | REDUCE FLUID FLOW RATES | $16,217 | $25,000 | Not Implemented |
NC0387 # 02 Y:2009 | 02 | 2009 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $51,343 | $72,000 | Not Implemented |
NC0387 # 09 Y:2009 | 09 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $712 | $351 | Not Implemented |
NC0387 # 08 Y:2009 | 08 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,156 | $85,555 | Implemented |
NC0387 # 07 Y:2009 | 07 | 2009 | DEVELOP A REPAIR/REPLACE POLICY | $2,019 | $2,198 | Not Implemented |
NC0387 # 06 Y:2009 | 06 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,447 | $100 | Implemented |
NC0387 # 05 Y:2009 | 05 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,105 | $7,000 | Not Implemented |
NC0387 # 04 Y:2009 | 04 | 2009 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $21,000 | $25,000 | Not Implemented |
NC0387 # 03 Y:2009 | 03 | 2009 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $44,613 | $45,000 | Not Implemented |
NC0387 # 01 Y:2009 | 01 | 2009 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $202,240 | $400,000 | Not Implemented |
NC0334 # 05 Y:2006 | 05 | 2006 | REDUCE VENTILATION AIR | $10,892 | $4,000 | Implemented |
NC0334 # 04 Y:2006 | 04 | 2006 | RECOVER AND REUSE COOLING WATER | $1,680 | $620 | Implemented |
NC0334 # 03 Y:2006 | 03 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,466 | $500 | Implemented |