Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
736
matching recommendationsNAICS | 3353 | Electrical Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0120 # 07 Y:2018 | 07 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,377 | $2,251 | Implemented |
WM0120 # 08 Y:2018 | 08 | 2018 | INSTALL OCCUPANCY SENSORS | $1,092 | $1,439 | Not Implemented |
WM0120 # 09 Y:2018 | 09 | 2018 | USE PHOTOCELL CONTROLS | $793 | $1,120 | Not Implemented |
WM0120 # 10 Y:2018 | 10 | 2018 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $660 | $405 | Not Implemented |
WM0120 # 11 Y:2018 | 11 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $408 | $0 | Not Implemented |
WM0120 # 12 Y:2018 | 12 | 2018 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $258 | $0 | Not Implemented |
WM0120 # 13 Y:2018 | 13 | 2018 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $135 | $328 | Not Implemented |
MZ0245 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,959 | $47,658 | Implemented |
MZ0245 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,450 | $2,183 | Implemented |
MZ0245 # 03 Y:2017 | 03 | 2017 | OPTIMIZE PLANT POWER FACTOR | $13,572 | $12,250 | Not Implemented |
MZ0245 # 04 Y:2017 | 04 | 2017 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,371 | $0 | Not Implemented |
MZ0245 # 05 Y:2017 | 05 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,041 | $3,300 | Not Implemented |
MZ0245 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,755 | $150 | Implemented |
MZ0245 # 07 Y:2017 | 07 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,321 | $1,300 | Implemented |
MZ0245 # 08 Y:2017 | 08 | 2017 | INSTALL OCCUPANCY SENSORS | $3,089 | $2,730 | Implemented |
MZ0245 # 09 Y:2017 | 09 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,202 | $500 | Implemented |
MZ0245 # 10 Y:2017 | 10 | 2017 | USE PHOTOCELL CONTROLS | $1,335 | $906 | Not Implemented |
MZ0245 # 11 Y:2017 | 11 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,076 | $250 | Implemented |
UM0487 # 01 Y:2017 | 01 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,265 | $4,500 | n/a |
UM0487 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,701 | $105,530 | n/a |
UM0487 # 03 Y:2017 | 03 | 2017 | COVER OPEN TANKS | $23,071 | $2,137 | n/a |
AM0729 # 01 Y:2017 | 01 | 2017 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $6,900 | $0 | Implemented |
AM0729 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,965 | $28,840 | Implemented |
AM0729 # 03 Y:2017 | 03 | 2017 | OPTIMIZE PLANT POWER FACTOR | $3,490 | $3,740 | Implemented |
AM0729 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,930 | $1,000 | Implemented |