IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,801

matching recommendations
Reset
NAICS 336 Transportation Equipment Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0338 # 05 Y:2006 05 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $8,416 $16,843 Implemented
NC0338 # 06 Y:2006 06 2006 COVER OPEN TANKS $1,097 $1,600 Implemented
UM0299 # 01 Y:2006 01 2006 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE $36,291 $720 Implemented
UM0299 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $18,496 $8,700 Implemented
UM0299 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,108 $9,353 Implemented
UM0299 # 04 Y:2006 04 2006 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $11,706 $738 Implemented
UM0299 # 05 Y:2006 05 2006 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $5,156 $25 Implemented
UM0299 # 07 Y:2006 07 2006 INSTALL SKYLIGHTS $208 $184 Implemented
IC0116 # 01 Y:2006 01 2006 RECOVER WASTE HEAT FROM EQUIPMENT $3,603 $6,000 Implemented
IC0116 # 02 Y:2006 02 2006 RECOVER WASTE HEAT FROM EQUIPMENT $3,321 $1,100 Implemented
IC0116 # 04 Y:2006 04 2006 INSTALL TIMERS AND/OR THERMOSTATS $15,127 $218 Implemented
IC0116 # 05 Y:2006 05 2006 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $4,114 $0 Implemented
BD0309 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,400 $1,800 Implemented
BD0309 # 03 Y:2006 03 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,190 $0 Implemented
BD0309 # 04 Y:2006 04 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $809 $1,000 Implemented
BD0309 # 05 Y:2006 05 2006 RECOVER WASTE HEAT FROM EQUIPMENT $7,023 $1,880 Implemented
BD0309 # 06 Y:2006 06 2006 INSTALL OCCUPANCY SENSORS $653 $1,200 Implemented
BD0309 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $309 $475 Implemented
UD0740 # 02 Y:2006 02 2006 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $107,569 $256,000 Implemented
UD0740 # 03 Y:2006 03 2006 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $56,879 $252,100 Implemented
UD0740 # 05 Y:2006 05 2006 USE PHOTOCELL CONTROLS $42,737 $0 Implemented
UD0740 # 07 Y:2006 07 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,352 $2,280 Implemented
UD0740 # 09 Y:2006 09 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $3,096 $0 Implemented
UD0740 # 10 Y:2006 10 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,805 $1,500 Implemented
UD0740 # 11 Y:2006 11 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,326 $1,700 Implemented