Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
401
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0086 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,086 | $29,396 | Implemented |
UA0086 # 02 Y:2012 | 02 | 2012 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $7,370 | $1,353 | Implemented |
UA0086 # 03 Y:2012 | 03 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $7,367 | $2,548 | Not Implemented |
UA0086 # 04 Y:2012 | 04 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,694 | $800 | Not Implemented |
UA0086 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,645 | $2,200 | Implemented |
UA0086 # 06 Y:2012 | 06 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $481 | $613 | Implemented |
UA0086 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,174 | $30,000 | Not Implemented |
UA0084 # 01 Y:2012 | 01 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $23,489 | $160 | Implemented |
UA0084 # 02 Y:2012 | 02 | 2012 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,919 | $640 | Not Implemented |
UA0084 # 03 Y:2012 | 03 | 2012 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $5,106 | $2,157 | Implemented |
UA0084 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,492 | $9,195 | Implemented |
UA0084 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,491 | $800 | Not Implemented |
UA0084 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,837 | $4,093 | Not Implemented |
UA0084 # 07 Y:2012 | 07 | 2012 | PAY UTILITY BILLS ON TIME | $812 | $30 | Implemented |
UA0082 # 01 Y:2012 | 01 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $89,005 | $0 | Not Implemented |
UA0082 # 02 Y:2012 | 02 | 2012 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $25,747 | $24,000 | Not Implemented |
UA0082 # 03 Y:2012 | 03 | 2012 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $21,616 | $1,199 | Not Implemented |
UA0082 # 04 Y:2012 | 04 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $2,439 | $0 | Not Implemented |
UA0082 # 05 Y:2012 | 05 | 2012 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $1,097 | $171 | Not Implemented |
UA0082 # 06 Y:2012 | 06 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $17,850 | $26,100 | Not Implemented |
UA0082 # 07 Y:2012 | 07 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $19,536 | $6,566 | Not Implemented |
UA0082 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,883 | $7,495 | Implemented |
UA0082 # 09 Y:2012 | 09 | 2012 | OPTIMIZE PLANT POWER FACTOR | $18,443 | $21,400 | Not Implemented |
UA0082 # 10 Y:2012 | 10 | 2012 | INSTALL OCCUPANCY SENSORS | $2,406 | $116 | Not Implemented |
UA0078 # 01 Y:2012 | 01 | 2012 | BURN A LESS EXPENSIVE GRADE OF FUEL | $217,328 | $9,277 | Not Implemented |