IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,773

matching recommendations
Reset
NAICS 336 Transportation Equipment Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA0084 # 02 Y:2012 02 2012 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $6,919 $640 Not Implemented
UA0084 # 03 Y:2012 03 2012 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE $5,106 $2,157 Implemented
UA0084 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,492 $9,195 Implemented
UA0084 # 05 Y:2012 05 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $10,491 $800 Not Implemented
UA0084 # 06 Y:2012 06 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,837 $4,093 Not Implemented
UA0084 # 07 Y:2012 07 2012 PAY UTILITY BILLS ON TIME $812 $30 Implemented
LL0369 # 01 Y:2012 01 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $54,656 $11,200 Not Implemented
LL0369 # 02 Y:2012 02 2012 USE PHOTOCELL CONTROLS $3,740 $120 Not Implemented
LL0369 # 03 Y:2012 03 2012 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $2,943 $630 Not Implemented
LL0369 # 04 Y:2012 04 2012 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $1,500 $660 Not Implemented
LL0369 # 05 Y:2012 05 2012 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $584 $735 Not Implemented
LL0369 # 06 Y:2012 06 2012 INSTALL OCCUPANCY SENSORS $419 $735 Not Implemented
LL0369 # 07 Y:2012 07 2012 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $200 $155 Not Implemented
LL0369 # 08 Y:2012 08 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $188 $213 Not Implemented
LL0369 # 09 Y:2012 09 2012 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $10,920 $2,084 Not Implemented
WM0008 # 01 Y:2012 01 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $16,760 $0 Not Implemented
WM0008 # 02 Y:2012 02 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $8,834 $0 Not Implemented
WM0008 # 03 Y:2012 03 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,802 $0 Not Implemented
WM0008 # 04 Y:2012 04 2012 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER $40,676 $83,400 Not Implemented
WM0008 # 05 Y:2012 05 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,551 $1,000 Not Implemented
WM0008 # 06 Y:2012 06 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $2,737 $0 Not Implemented
WM0008 # 07 Y:2012 07 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $432 $520 Not Implemented
WM0008 # 08 Y:2012 08 2012 INSTALL OCCUPANCY SENSORS $1,209 $990 Not Implemented
WM0008 # 09 Y:2012 09 2012 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $9,137 $3,034 Not Implemented
WM0008 # 10 Y:2012 10 2012 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $840 $400 Not Implemented