Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
248
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0519 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,100 | $15,300 | Implemented |
AM0519 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,890 | $500 | Implemented |
AM0519 # 03 Y:2006 | 03 | 2006 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,500 | $3,000 | Implemented |
AM0519 # 04 Y:2006 | 04 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $770 | $14 | Not Implemented |
AM0519 # 05 Y:2006 | 05 | 2006 | INSTALL SKYLIGHTS | $900 | $1,500 | Not Implemented |
AM0519 # 06 Y:2006 | 06 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $575 | $1,000 | Not Implemented |
AM0519 # 07 Y:2006 | 07 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $450 | $250 | Implemented |
AM0519 # 08 Y:2006 | 08 | 2006 | PAY UTILITY BILLS ON TIME | $280 | $0 | Implemented |
AM0519 # 09 Y:2006 | 09 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $145 | $0 | Not Implemented |
AM0519 # 10 Y:2006 | 10 | 2006 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $130 | $0 | Not Implemented |
TA0116 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,371 | $16,650 | Not Implemented |
TA0116 # 02 Y:2006 | 02 | 2006 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $13,000 | $0 | Not Implemented |
TA0116 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,000 | $240 | Not Implemented |
TA0116 # 04 Y:2006 | 04 | 2006 | INSTALL SYSTEM TO COLLECT SCRAP | $21,734 | $1,600 | Not Implemented |
TA0116 # 05 Y:2006 | 05 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,820 | $0 | Not Implemented |
TA0109 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,692 | $1,000 | Not Implemented |
TA0109 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $45,200 | $25,500 | Not Implemented |
TA0109 # 03 Y:2005 | 03 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,870 | $-7,870 | Not Implemented |
TA0109 # 04 Y:2005 | 04 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,691 | $5,500 | Not Implemented |
TA0109 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $502 | $616 | Not Implemented |
TA0109 # 06 Y:2005 | 06 | 2005 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $356 | $0 | Not Implemented |
TA0106 # 01 Y:2005 | 01 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $28,674 | $-14,337 | Implemented |
TA0106 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,775 | $175 | Implemented |
TA0106 # 03 Y:2005 | 03 | 2005 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $4,400 | $185 | Not Implemented |
TA0106 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,400 | $12,395 | Implemented |