Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsNAICS | 3363 | Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0590 # 13 Y:2020 | 13 | 2020 | DEVELOP A REPAIR/REPLACE POLICY | $101 | $271 | Implemented |
WV0590 # 12 Y:2020 | 12 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $768 | $100 | Implemented |
WV0590 # 11 Y:2020 | 11 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,693 | $1,000 | Implemented |
WV0590 # 09 Y:2020 | 09 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,957 | $813 | Implemented |
WV0590 # 07 Y:2020 | 07 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,881 | $1,468 | Implemented |
WV0590 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $16,468 | $5,109 | Implemented |
WV0590 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $41,451 | $66,168 | Implemented |
NC0626 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,564 | $40,273 | Implemented |
NC0626 # 07 Y:2019 | 07 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,977 | $200 | Implemented |
NC0626 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,034 | $135 | Implemented |
NC0543 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $311 | $80 | Implemented |
NC0543 # 08 Y:2015 | 08 | 2015 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $192 | $500 | Implemented |
NC0543 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,805 | $100 | Implemented |
NC0543 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,402 | $100 | Implemented |
NC0543 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,078 | $68,997 | Implemented |
NC0531 # 01 Y:2014 | 01 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,220 | $200 | Implemented |
NC0531 # 07 Y:2014 | 07 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $2,202 | $4,256 | Implemented |
NC0531 # 05 Y:2014 | 05 | 2014 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $625 | $100 | Implemented |
NC0531 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $836 | $240 | Implemented |
NC0531 # 02 Y:2014 | 02 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $80,544 | $28,000 | Implemented |