Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
204
matching recommendationsNAICS | 33634 | Motor Vehicle Brake System Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2216 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,213 | $960 | Implemented |
UL2216 # 10 Y:2022 | 10 | 2022 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $4,758 | $500 | Not Implemented |
UD1031 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,382 | $0 | Implemented |
UD1031 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,188 | $676 | Implemented |
UD1031 # 07 Y:2022 | 07 | 2022 | COVER OPEN TANKS | $7,338 | $15,000 | Not Implemented |
UD1031 # 05 Y:2022 | 05 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,586 | $0 | Implemented |
UD1031 # 11 Y:2022 | 11 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $909 | $0 | Implemented |
UD1031 # 15 Y:2022 | 15 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,659 | $7,500 | Not Implemented |
UD1031 # 12 Y:2022 | 12 | 2022 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $2,847 | $1,000 | Not Implemented |
UD1031 # 13 Y:2022 | 13 | 2022 | OPTIMIZE PLANT POWER FACTOR | $1,446 | $4,227 | Not Implemented |
UD1031 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $31,642 | $15,000 | Not Implemented |
UD1031 # 04 Y:2022 | 04 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,863 | $10,000 | Not Implemented |
UD1031 # 10 Y:2022 | 10 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,888 | $23,132 | Not Implemented |
UD1031 # 08 Y:2022 | 08 | 2022 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $30,918 | $30,918 | Not Implemented |
UD1031 # 09 Y:2022 | 09 | 2022 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $6,625 | $5,000 | Not Implemented |
UD1031 # 14 Y:2022 | 14 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,264 | $7,500 | Not Implemented |
UD1031 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,133 | $5,000 | Not Implemented |
NC0661 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,982 | $3,360 | n/a |
NC0661 # 02 Y:2021 | 02 | 2021 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,073 | $27,600 | n/a |
NC0661 # 03 Y:2021 | 03 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,376 | $4,000 | n/a |
NC0661 # 04 Y:2021 | 04 | 2021 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $2,158 | $2,300 | n/a |
TT0223 # 10 Y:2019 | 10 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $159 | $200 | Not Implemented |
TT0223 # 08 Y:2019 | 08 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,166 | $1,000 | Not Implemented |
TT0223 # 09 Y:2019 | 09 | 2019 | OPTIMIZE PLANT POWER FACTOR | $657 | $1,500 | Not Implemented |
TT0223 # 05 Y:2019 | 05 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,556 | $7,425 | Not Implemented |