Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
142
matching recommendationsNAICS | 336350 | Motor Vehicle Transmission and Power Train Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0236 # 03 Y:2020 | 03 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,481 | $0 | Implemented |
IC0236 # 01 Y:2020 | 01 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,924 | $30,183 | Implemented |
UD0984 # 05 Y:2018 | 05 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $13,616 | $10,000 | Implemented |
UD0984 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $852 | $750 | Implemented |
UD0984 # 09 Y:2018 | 09 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,474 | $11,000 | Implemented |
UD0984 # 06 Y:2018 | 06 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,684 | $0 | Implemented |
UD0984 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,981 | $14,930 | Implemented |
UD0984 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,566 | $1,500 | Implemented |
IP0092 # 01 Y:2017 | 01 | 2017 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,211 | $0 | Implemented |
IP0092 # 07 Y:2017 | 07 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $112,756 | $41,810 | Implemented |
IP0092 # 06 Y:2017 | 06 | 2017 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $8,898 | $1,119 | Implemented |
IP0092 # 05 Y:2017 | 05 | 2017 | INSTALL OCCUPANCY SENSORS | $635 | $42 | Implemented |
IP0092 # 04 Y:2017 | 04 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $546 | $31 | Implemented |
IP0092 # 03 Y:2017 | 03 | 2017 | PAY BILLS ON TIME TO AVOID LATE FEES | $7,288 | $0 | Implemented |
IP0092 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $876 | $0 | Implemented |
UD0977 # 06 Y:2017 | 06 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $16,048 | $2,000 | Implemented |
UD0977 # 08 Y:2017 | 08 | 2017 | ADD AREA LIGHTING SWITCHES | $745 | $0 | Implemented |
UD0977 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,231 | $0 | Implemented |
UD0977 # 01 Y:2017 | 01 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $12,684 | $6,500 | Implemented |
UD0977 # 02 Y:2017 | 02 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,960 | $0 | Implemented |
TT0196 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,605 | $3,050 | Implemented |
NC0568 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $179,170 | $887,700 | Implemented |
NC0568 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,081 | $200 | Implemented |
IP0061 # 06 Y:2016 | 06 | 2016 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,664 | $3,260 | Implemented |
IP0061 # 08 Y:2016 | 08 | 2016 | RECYCLE WHITE WATER | $61,804 | $36,000 | Implemented |