Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,252
matching recommendationsNAICS | 336390 | Other Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0069 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,126 | $1,300 | Not Implemented |
UA0069 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,916 | $3,200 | Not Implemented |
UA0069 # 05 Y:2011 | 05 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $678 | $2,578 | Not Implemented |
UA0069 # 06 Y:2011 | 06 | 2011 | USE OPTIMUM THICKNESS INSULATION | $25,829 | $16,900 | Not Implemented |
UA0069 # 07 Y:2011 | 07 | 2011 | USE OPTIMUM THICKNESS INSULATION | $5,314 | $1,750 | Not Implemented |
UA0069 # 08 Y:2011 | 08 | 2011 | USE OPTIMUM THICKNESS INSULATION | $6,558 | $7,600 | Not Implemented |
UA0069 # 09 Y:2011 | 09 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,865 | $24,690 | Implemented |
UA0069 # 10 Y:2011 | 10 | 2011 | INSTALL OCCUPANCY SENSORS | $596 | $398 | Not Implemented |
UA3016 # 01 Y:2011 | 01 | 2011 | BURN WOOD BY-PRODUCTS FOR HEAT | $19,294 | $53,500 | Not Implemented |
UA3016 # 02 Y:2011 | 02 | 2011 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $3,721 | $3,550 | Not Implemented |
UA3016 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,180 | $1,500 | Implemented |
UA3016 # 04 Y:2011 | 04 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,387 | $2,291 | Not Implemented |
UA3016 # 05 Y:2011 | 05 | 2011 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,784 | $2,000 | Not Implemented |
IA0473 # 01 Y:2011 | 01 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $695 | $1,100 | Not Implemented |
IA0473 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,500 | $105 | Implemented |
IA0473 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,238 | $4,669 | Implemented |
IA0473 # 04 Y:2011 | 04 | 2011 | INSTALL OCCUPANCY SENSORS | $1,472 | $426 | Not Implemented |
IA0473 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $615 | $1,273 | Implemented |
IA0473 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $468 | $954 | Not Implemented |
GT0882 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,634 | $0 | Implemented |
GT0882 # 02 Y:2011 | 02 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,201 | $0 | Not Implemented |
GT0882 # 03 Y:2011 | 03 | 2011 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $28,143 | $70,000 | Not Implemented |
GT0882 # 04 Y:2011 | 04 | 2011 | METER WASTE WATER | $3,614 | $6,000 | Not Implemented |
GT0882 # 05 Y:2011 | 05 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $16,076 | $55,000 | Implemented |
GT0882 # 06 Y:2011 | 06 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $31,792 | $136,000 | Implemented |