Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
723
matching recommendationsNAICS | 33641 | Aerospace Product and Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0321 # 08 Y:2011 | 08 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,803 | $18,000 | Implemented |
GT0881 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,620 | $15,500 | Implemented |
GT0881 # 08 Y:2011 | 08 | 2011 | COMBINE UTILITY METERS | $14,342 | $10,000 | Implemented |
WV0420 # 03 Y:2011 | 03 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,569 | $14,510 | Implemented |
WV0420 # 04 Y:2011 | 04 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,500 | $4,500 | Implemented |
WV0420 # 05 Y:2011 | 05 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $764 | $480 | Implemented |
OK0802 # 02 Y:2010 | 02 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,400 | $1,550 | Implemented |
OK0802 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $1,998 | $13,149 | Implemented |
OK0802 # 05 Y:2010 | 05 | 2010 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $11,414 | $51,875 | Implemented |
OK0802 # 06 Y:2010 | 06 | 2010 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,918 | $2,775 | Implemented |
OK0802 # 07 Y:2010 | 07 | 2010 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $30,411 | $45,000 | Implemented |
OK0802 # 08 Y:2010 | 08 | 2010 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $23,800 | $15,600 | Implemented |
OK0802 # 09 Y:2010 | 09 | 2010 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,625 | $0 | Implemented |
OK0802 # 10 Y:2010 | 10 | 2010 | COMBINE UTILITY METERS | $936 | $175 | Implemented |
OK0801 # 01 Y:2010 | 01 | 2010 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $6,511 | $78,169 | Implemented |
OK0801 # 02 Y:2010 | 02 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,599 | $34,948 | Implemented |
OK0801 # 03 Y:2010 | 03 | 2010 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $9,699 | $3,000 | Implemented |
OK0801 # 04 Y:2010 | 04 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $995 | $2,625 | Implemented |
OK0801 # 12 Y:2010 | 12 | 2010 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $4,196 | $21,075 | Implemented |
CO0644 # 01 Y:2010 | 01 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,520 | $1,000 | Implemented |
CO0644 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,750 | $1,000 | Implemented |
CO0644 # 03 Y:2010 | 03 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,030 | $35,000 | Implemented |
CO0644 # 04 Y:2010 | 04 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,750 | $15,000 | Implemented |
CO0644 # 06 Y:2010 | 06 | 2010 | REDUCE VENTILATION AIR | $1,390 | $12,400 | Implemented |
MI0196 # 01 Y:2010 | 01 | 2010 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $157,910 | $102,500 | Implemented |