Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
73
matching recommendationsNAICS | 3369 | Other Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0890 # 08 Y:2013 | 08 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,203 | $0 | Implemented |
IP0016 # 01 Y:2013 | 01 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,083 | $0 | Implemented |
IP0016 # 04 Y:2013 | 04 | 2013 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $7,284 | $1,400 | Implemented |
IP0016 # 08 Y:2013 | 08 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,271 | $1,400 | Implemented |
TT0106 # 02 Y:2013 | 02 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,063 | $720 | Implemented |
OK0843 # 01 Y:2013 | 01 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,582 | $3,116 | Implemented |
OK0843 # 07 Y:2013 | 07 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,864 | $7,326 | Implemented |
OK0843 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,261 | $20,748 | Implemented |
OK0843 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,466 | $0 | Implemented |
OK0843 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,402 | $1,000 | Implemented |
UA0089 # 01 Y:2012 | 01 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $7,437 | $680 | Implemented |
UA0089 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,625 | $200 | Implemented |
NC0472 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,563 | $16,950 | Implemented |
NC0472 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $188 | $50 | Implemented |
NC0472 # 05 Y:2012 | 05 | 2012 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $24 | $0 | Implemented |
UM0375 # 03 Y:2010 | 03 | 2010 | INSTALL OCCUPANCY SENSORS | $7,646 | $4,232 | Implemented |
UM0375 # 04 Y:2010 | 04 | 2010 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $27,796 | $140,490 | Implemented |
UM0375 # 05 Y:2010 | 05 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $16,802 | $5,500 | Implemented |
UM0375 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $126,231 | $236,764 | Implemented |
UM0375 # 02 Y:2010 | 02 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $16,709 | $4,000 | Implemented |
UA0041 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $55,100 | $119,700 | Implemented |
UA0041 # 04 Y:2010 | 04 | 2010 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $216,130 | $0 | Implemented |
UA0041 # 05 Y:2010 | 05 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $76,495 | $0 | Implemented |
UA0041 # 07 Y:2010 | 07 | 2010 | INSULATE BARE EQUIPMENT | $1,020 | $2,450 | Implemented |
UA0041 # 08 Y:2010 | 08 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,050 | $2 | Implemented |