Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
148
matching recommendationsNAICS | 339113 | Surgical Appliance and Supplies Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0241 # 08 Y:2013 | 08 | 2013 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,942 | $2,196 | Implemented |
MI0241 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,593 | $1,660 | Implemented |
MI0241 # 11 Y:2013 | 11 | 2013 | INSULATE BARE EQUIPMENT | $686 | $1,520 | Implemented |
MI0233 # 01 Y:2012 | 01 | 2012 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $246,388 | $33,021 | Implemented |
MI0233 # 02 Y:2012 | 02 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $150,126 | $80 | Implemented |
MI0233 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,400 | $1,660 | Implemented |
MI0233 # 08 Y:2012 | 08 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,430 | $2,665 | Implemented |
MI0233 # 09 Y:2012 | 09 | 2012 | INSTALL OCCUPANCY SENSORS | $5,193 | $800 | Implemented |
MI0233 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,631 | $2,050 | Implemented |
MI0233 # 11 Y:2012 | 11 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,084 | $80 | Implemented |
MI0233 # 12 Y:2012 | 12 | 2012 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $3,056 | $843 | Implemented |
AM0617 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,264 | $2,775 | Implemented |
AM0617 # 04 Y:2012 | 04 | 2012 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $2,146 | $0 | Implemented |
AM0617 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $2,056 | $1,562 | Implemented |
AM0617 # 06 Y:2012 | 06 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,871 | $64 | Implemented |
AM0617 # 07 Y:2012 | 07 | 2012 | RECYCLE WHITE WATER | $1,161 | $7,179 | Implemented |
AM0617 # 08 Y:2012 | 08 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $911 | $5,377 | Implemented |
AM0617 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $630 | $300 | Implemented |
LE0311 # 01 Y:2011 | 01 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $40,488 | $240 | Implemented |
LE0311 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,691 | $5,441 | Implemented |
LE0311 # 06 Y:2011 | 06 | 2011 | INSTALL OCCUPANCY SENSORS | $659 | $1,875 | Implemented |
LE0311 # 07 Y:2011 | 07 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $458 | $0 | Implemented |
LE0311 # 08 Y:2011 | 08 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $226 | $60 | Implemented |
UF0436 # 01 Y:2010 | 01 | 2010 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $493 | $388 | Implemented |
UF0436 # 04 Y:2010 | 04 | 2010 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $13,947 | $350 | Implemented |