Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
445
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0491 # 05 Y:2005 | 05 | 2005 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $730 | $1,300 | Not Implemented |
OR0491 # 06 Y:2005 | 06 | 2005 | INSTALL OCCUPANCY SENSORS | $2,440 | $1,900 | Not Implemented |
OR0491 # 07 Y:2005 | 07 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $7,040 | $10,650 | Not Implemented |
OR0491 # 08 Y:2005 | 08 | 2005 | OPTIMIZE PLANT POWER FACTOR | $650 | $1,800 | Not Implemented |
OR0490 # 01 Y:2005 | 01 | 2005 | USE LESS WASTEFUL PACKAGING | $35,000 | $1,000 | Not Implemented |
OR0490 # 02 Y:2005 | 02 | 2005 | USE LESS WASTEFUL PACKAGING | $23,500 | $1,000 | Not Implemented |
OR0490 # 03 Y:2005 | 03 | 2005 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $24,000 | $0 | Not Implemented |
OR0490 # 04 Y:2005 | 04 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $10,400 | $1,000 | Not Implemented |
OR0490 # 05 Y:2005 | 05 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,600 | $0 | Not Implemented |
OR0490 # 06 Y:2005 | 06 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $8,100 | $1,800 | Not Implemented |
OR0490 # 07 Y:2005 | 07 | 2005 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,720 | $0 | Not Implemented |
OR0490 # 08 Y:2005 | 08 | 2005 | OPTIMIZE PLANT POWER FACTOR | $2,750 | $5,600 | Not Implemented |
OR0484 # 01 Y:2005 | 01 | 2005 | USE RADIANT HEATER FOR SPOT HEATING | $41,089 | $40,143 | Not Implemented |
OR0484 # 02 Y:2005 | 02 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,710 | $400 | Not Implemented |
OR0484 # 03 Y:2005 | 03 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $847 | $1,013 | Implemented |
OR0483 # 01 Y:2005 | 01 | 2005 | RECOVER AND REUSE WASTE MATERIAL | $21,624 | $0 | Implemented |
OR0483 # 02 Y:2005 | 02 | 2005 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $24,290 | $4,400 | Implemented |
OR0483 # 03 Y:2005 | 03 | 2005 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $21,300 | $5,100 | Implemented |
OR0483 # 04 Y:2005 | 04 | 2005 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $8,960 | $3,000 | Implemented |
OR0483 # 05 Y:2005 | 05 | 2005 | BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT | $41,000 | $69,000 | Implemented |
OR0483 # 06 Y:2005 | 06 | 2005 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $40,390 | $72,000 | Implemented |
OR0483 # 07 Y:2005 | 07 | 2005 | USE HEAT EXCHANGE FLUIDS INSTEAD OF STEAM IN PIPELINE TRACING SYSTEMS | $5,131 | $15,000 | Not Implemented |
OR0481 # 01 Y:2005 | 01 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $32,471 | $0 | Not Implemented |
OR0481 # 02 Y:2005 | 02 | 2005 | INSTALL SET-BACK TIMERS | $2,880 | $300 | Not Implemented |
OR0481 # 03 Y:2005 | 03 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $25,000 | $26,000 | Implemented |