Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,785
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0226 # 05 Y:2023 | 05 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $4,421 | $3,000 | Not Implemented |
DL0226 # 06 Y:2023 | 06 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,451 | $0 | Implemented |
DL0226 # 07 Y:2023 | 07 | 2023 | REDUCE VENTILATION AIR | $1,643 | $57 | Implemented |
DL0226 # 08 Y:2023 | 08 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $6,284 | $3,000 | Not Implemented |
DL0226 # 09 Y:2023 | 09 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,355 | $9,585 | Implemented |
DL0226 # 10 Y:2023 | 10 | 2023 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $56,102 | $91,218 | Implemented |
LE0554 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,649 | $26,194 | Implemented |
LE0554 # 02 Y:2023 | 02 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $2,747 | $5,000 | Implemented |
LE0554 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,873 | $35,440 | Implemented |
LE0554 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,979 | $40,491 | Implemented |
LE0554 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,367 | $4,000 | Implemented |
LE0554 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $873 | $2,700 | Implemented |
LE0554 # 07 Y:2023 | 07 | 2023 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $31,394 | $144,000 | Not Implemented |
LE0554 # 08 Y:2023 | 08 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,658 | $49,017 | Not Implemented |
LE0554 # 09 Y:2023 | 09 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $193,840 | $880,000 | Not Implemented |
LE0554 # 10 Y:2023 | 10 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $18,296 | $86,535 | Implemented |
LE0554 # 11 Y:2023 | 11 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $44,665 | $369,354 | Not Implemented |
NL0087 # 01 Y:2023 | 01 | 2023 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $491,419 | $1,990,800 | n/a |
NL0087 # 02 Y:2023 | 02 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $254,315 | $454,461 | n/a |
NL0087 # 03 Y:2023 | 03 | 2023 | REPAIR OR REPLACE STEAM TRAPS | $17,666 | $50 | n/a |
NL0087 # 04 Y:2023 | 04 | 2023 | USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS | $12,625 | $8,000 | n/a |
NL0087 # 05 Y:2023 | 05 | 2023 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $11,616 | $7,640 | n/a |
NL0087 # 06 Y:2023 | 06 | 2023 | RECOVER AND REUSE WASTE MATERIAL | $10,817 | $3,660 | n/a |
NL0087 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,789 | $100 | n/a |
NL0087 # 08 Y:2023 | 08 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,019 | $768 | n/a |