IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

445

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0659 # 04 Y:2015 04 2015 INSULATE BARE EQUIPMENT $6,192 $8,000 Implemented
OR0659 # 05 Y:2015 05 2015 IMPROVE COMBUSTION CONTROL CAPABILITY $4,259 $5,617 Not Implemented
OR0659 # 06 Y:2015 06 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,165 $3,410 Not Implemented
OR0659 # 07 Y:2015 07 2015 INSULATE BARE EQUIPMENT $1,353 $8,000 Implemented
OR0659 # 08 Y:2015 08 2015 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,463 $0 Not Implemented
OR0655 # 01 Y:2015 01 2015 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $26,151 $0 Not Implemented
OR0655 # 02 Y:2015 02 2015 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,161 $1,000 Implemented
OR0655 # 03 Y:2015 03 2015 TURN OFF EQUIPMENT WHEN NOT IN USE $20,211 $1,000 Not Implemented
OR0655 # 04 Y:2015 04 2015 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $175,008 $188,400 Not Implemented
OR0655 # 05 Y:2015 05 2015 FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM $15,571 $19,050 Not Implemented
OR0655 # 06 Y:2015 06 2015 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $180,695 $251,760 Not Implemented
OR0655 # 07 Y:2015 07 2015 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $51,916 $126,000 Not Implemented
OR0655 # 08 Y:2015 08 2015 RECOVER WASTE HEAT FROM EQUIPMENT $4,958 $7,816 Not Implemented
OR0655 # 09 Y:2015 09 2015 USE SOLAR HEAT TO MAKE ELECTRICTY $2,480 $20,979 Not Implemented
OR0654 # 01 Y:2015 01 2015 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $1,067,158 $300,000 Implemented
OR0654 # 02 Y:2015 02 2015 MODIFY WORKLOAD $23,248 $10,000 Implemented
OR0654 # 03 Y:2015 03 2015 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $115,650 $50,000 Implemented
OR0654 # 04 Y:2015 04 2015 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,588 $5,986 Implemented
OR0654 # 05 Y:2015 05 2015 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $6,722 $60,000 Not Implemented
OR0654 # 06 Y:2015 06 2015 USE SOLAR HEAT TO MAKE ELECTRICTY $2,026 $9,325 Implemented
OR0631 # 01 Y:2014 01 2014 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $11,360 $250 Implemented
OR0631 # 02 Y:2014 02 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,168 $5,544 Not Implemented
OR0631 # 03 Y:2014 03 2014 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,567 $1,634 Implemented
OR0631 # 04 Y:2014 04 2014 INSTALL / REPAIR INSULATION ON STEAM LINES $800 $417 Implemented
OR0629 # 01 Y:2014 01 2014 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $37,907 $21,000 Implemented