IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20,785

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0044 # 10 Y:1988 10 1988 OPTIMIZE PLANT POWER FACTOR $14,889 $19,500 Not Implemented
OR0044 # 11 Y:1988 11 1988 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $1,525 $3,063 Implemented
OR0045 # 01 Y:1988 01 1988 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $1,601 $320 Not Implemented
OR0045 # 02 Y:1988 02 1988 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $614 $513 Not Implemented
OR0045 # 03 Y:1988 03 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $61 $64 Not Implemented
OR0045 # 04 Y:1988 04 1988 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $3,612 $5,792 Not Implemented
OR0045 # 05 Y:1988 05 1988 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,758 $8,921 Implemented
OR0045 # 06 Y:1988 06 1988 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $1,542 $3,258 Not Implemented
OR0046 # 01 Y:1989 01 1989 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $3,516 $0 Implemented
OR0046 # 02 Y:1989 02 1989 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $1,907 $0 Implemented
OR0046 # 03 Y:1989 03 1989 INSULATE FEEDWATER TANK $678 $259 Not Implemented
OR0046 # 04 Y:1989 04 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $106 $100 Implemented
OR0046 # 05 Y:1989 05 1989 OPTIMIZE PLANT POWER FACTOR $4,640 $4,500 Implemented
OR0046 # 06 Y:1989 06 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,573 $42,000 Implemented
OR0046 # 07 Y:1989 07 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $280 $500 Not Implemented
AM0052 # 01 Y:1989 01 1989 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $30,343 $60,000 Implemented
AM0052 # 02 Y:1989 02 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $14,450 $10,000 Not Implemented
AM0052 # 03 Y:1989 03 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,260 $300 Implemented
AM0052 # 04 Y:1989 04 1989 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $3,080 $1,400 Implemented
AM0052 # 05 Y:1989 05 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,030 $303 Not Implemented
AM0052 # 06 Y:1989 06 1989 REPAIR AND ELIMINATE STEAM LEAKS $2,005 $600 Implemented
AM0052 # 07 Y:1989 07 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,490 $1,100 Implemented
AM0052 # 08 Y:1989 08 1989 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,415 $0 Implemented
AM0052 # 09 Y:1989 09 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $470 $300 Not Implemented
LT0138 # 01 Y:1988 01 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $648 $1,801 Not Implemented