Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
511
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0514 # 04 Y:2017 | 04 | 2017 | REDUCE EXCESS STEAM BLEEDING | $4,320 | $0 | Implemented |
UF0514 # 02 Y:2017 | 02 | 2017 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $7,847 | $20,000 | Implemented |
UF0514 # 03 Y:2017 | 03 | 2017 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $5,710 | $7,580 | Not Implemented |
UF0514 # 06 Y:2017 | 06 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,693 | $6,775 | Implemented |
UF0514 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,154 | $30,844 | Implemented |
UF0514 # 07 Y:2017 | 07 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,432 | $0 | Implemented |
UF0514 # 05 Y:2017 | 05 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,740 | $2,882 | Implemented |
UU0126 # 02 Y:2017 | 02 | 2017 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $27,838 | $3,980 | Implemented |
UU0126 # 05 Y:2017 | 05 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,358 | $90 | Implemented |
UU0126 # 01 Y:2017 | 01 | 2017 | MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT | $207,807 | $2,000,000 | Not Implemented |
UU0126 # 06 Y:2017 | 06 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,423 | $2,000 | Implemented |
UU0126 # 03 Y:2017 | 03 | 2017 | REPLACE BOILER | $26,315 | $176,427 | Not Implemented |
UU0126 # 04 Y:2017 | 04 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $14,977 | $8,120 | Not Implemented |
OR0696 # 01 Y:2017 | 01 | 2017 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $179,573 | $3,044 | Not Implemented |
OR0696 # 03 Y:2017 | 03 | 2017 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $2,365 | $5,880 | Not Implemented |
OR0696 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,910 | $10,116 | Not Implemented |
OR0696 # 02 Y:2017 | 02 | 2017 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $79,265 | $37,275 | Not Implemented |
LS0012 # 05 Y:2017 | 05 | 2017 | REDUCE EXCESSIVE BOILER BLOWDOWN | $3,685 | $4,250 | Not Implemented |
UF0513 # 03 Y:2017 | 03 | 2017 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $14,487 | $23,157 | Implemented |
UF0513 # 04 Y:2017 | 04 | 2017 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $7,542 | $0 | Implemented |
UF0513 # 02 Y:2017 | 02 | 2017 | ISOLATE HOT OR COLD EQUIPMENT | $25,893 | $3,150 | Implemented |
UF0513 # 08 Y:2017 | 08 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,095 | $5,053 | Implemented |
UF0513 # 06 Y:2017 | 06 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,848 | $10,386 | Not Implemented |
UF0513 # 07 Y:2017 | 07 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,443 | $1,481 | Implemented |
LS0012 # 06 Y:2017 | 06 | 2017 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $28,215 | $80,000 | Not Implemented |