Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsSIC | 202 | Dairy Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0404 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,243 | $0 | Implemented |
SF0404 # 03 Y:2011 | 03 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $257 | $22 | Implemented |
SF0404 # 04 Y:2011 | 04 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $17,934 | $5,426 | Implemented |
SF0404 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $697 | $1,356 | Implemented |
SF0404 # 10 Y:2011 | 10 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $676 | $1,569 | Implemented |
LL0356 # 13 Y:2011 | 13 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $80 | $66 | Implemented |
LL0356 # 08 Y:2011 | 08 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,666 | $360 | Implemented |
LL0356 # 05 Y:2011 | 05 | 2011 | INSULATE BARE EQUIPMENT | $6,412 | $1,127 | Implemented |
LL0356 # 02 Y:2011 | 02 | 2011 | INSULATE BARE EQUIPMENT | $9,420 | $840 | Implemented |
LL0356 # 01 Y:2011 | 01 | 2011 | INCREASE AMOUNT OF CONDENSATE RETURNED | $35,965 | $89,664 | Implemented |
BD0393 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $201 | $10 | Implemented |
BD0393 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $155 | $300 | Implemented |
BD0393 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,288 | $107,000 | Implemented |
UF0443 # 01 Y:2011 | 01 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,607 | $0 | Implemented |
UF0443 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $562 | $75 | Implemented |
UF0443 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,731 | $42,492 | Implemented |
UF0443 # 06 Y:2011 | 06 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $19,349 | $2,235 | Implemented |
SD0434 # 05 Y:2011 | 05 | 2011 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,400 | $2,063 | Implemented |
SD0434 # 02 Y:2011 | 02 | 2011 | INSTALL OCCUPANCY SENSORS | $7,897 | $1,387 | Implemented |
SD0434 # 01 Y:2011 | 01 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $799 | $100 | Implemented |
SF0394 # 06 Y:2011 | 06 | 2011 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,794 | $20,780 | Implemented |
SF0394 # 07 Y:2011 | 07 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $241 | $700 | Implemented |
SF0394 # 05 Y:2011 | 05 | 2011 | INSTALL OCCUPANCY SENSORS | $7,621 | $11,002 | Implemented |
SF0394 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,204 | $73 | Implemented |
SF0394 # 02 Y:2011 | 02 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $439 | $235 | Implemented |