IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

113

matching recommendations
Reset
SIC 202 Dairy Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0610 # 02 Y:2024 02 2024 REPAIR AND ELIMINATE STEAM LEAKS $12,954 $0 Implemented
SF0610 # 01 Y:2024 01 2024 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,215 $0 Implemented
SF0610 # 04 Y:2024 04 2024 HEAT WATER WITH EXHAUST HEAT $36,485 $30,037 Implemented
SF0610 # 03 Y:2024 03 2024 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $32,003 $15,909 Implemented
SF0610 # 06 Y:2024 06 2024 INSTALL OCCUPANCY SENSORS $8,502 $10,799 Implemented
SF0610 # 05 Y:2024 05 2024 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $31,683 $31,050 Implemented
SF0606 # 01 Y:2023 01 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,495 $1,440 Implemented
SF0606 # 02 Y:2023 02 2023 USE MINIMUM STEAM OPERATING PRESSURE $5,475 $60 Implemented
SF0606 # 04 Y:2023 04 2023 INSULATE BARE EQUIPMENT $5,279 $5,910 Implemented
SF0606 # 05 Y:2023 05 2023 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $4,502 $8,173 Implemented
SF0606 # 03 Y:2023 03 2023 INSULATE BARE EQUIPMENT $1,107 $564 Implemented
SF0601 # 04 Y:2023 04 2023 USE OPTIMUM THICKNESS INSULATION $3,765 $1,482 Implemented
SF0601 # 01 Y:2023 01 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $35,057 $0 Implemented
SF0601 # 06 Y:2023 06 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $14,700 $12,525 Implemented
SD0601 # 02 Y:2020 02 2020 INSTALL OCCUPANCY SENSORS $295 $504 Implemented
SD0601 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $139 $225 Implemented
SD0601 # 01 Y:2020 01 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $714 $1,555 Implemented
SD0592 # 05 Y:2020 05 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $2,751 $5,661 Implemented
SD0592 # 03 Y:2020 03 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,470 $13,092 Implemented
SD0592 # 02 Y:2020 02 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $34,440 $12,400 Implemented
SD0592 # 01 Y:2020 01 2020 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $61,433 $149,300 Implemented
SF0520 # 09 Y:2018 09 2018 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,289 $953 Implemented
SF0520 # 03 Y:2018 03 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,563 $136 Implemented
SF0520 # 04 Y:2018 04 2018 INSTALL / REPAIR INSULATION ON STEAM LINES $4,469 $4,039 Implemented
SF0520 # 05 Y:2018 05 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,296 $8,179 Implemented