Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
172
matching recommendationsSIC | 2038 | Frozen Specialties, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0198 # 01 Y:2017 | 01 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $9,284 | $50 | Implemented |
TT0198 # 02 Y:2017 | 02 | 2017 | INSULATE BARE EQUIPMENT | $7,752 | $3,175 | Implemented |
TT0198 # 05 Y:2017 | 05 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $329 | $1,600 | Implemented |
UA0179 # 04 Y:2017 | 04 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,851 | $250 | Implemented |
UA0179 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,243 | $1,165 | Implemented |
UA0179 # 09 Y:2017 | 09 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,242 | $1,015 | Implemented |
UA0179 # 08 Y:2017 | 08 | 2017 | INSULATE BARE EQUIPMENT | $429 | $247 | Implemented |
MZ0215 # 02 Y:2016 | 02 | 2016 | INSULATE BARE EQUIPMENT | $2,514 | $1,500 | Implemented |
MZ0215 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,397 | $8,400 | Implemented |
MZ0215 # 03 Y:2016 | 03 | 2016 | INSTALL OCCUPANCY SENSORS | $1,093 | $220 | Implemented |
NC0518 # 01 Y:2014 | 01 | 2014 | INSTALL AUTOMATIC PACKING EQUIPMENT | $1,248,000 | $800,000 | Implemented |
NC0518 # 07 Y:2014 | 07 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $524 | $100 | Implemented |
NC0518 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,276 | $100 | Implemented |
NC0518 # 09 Y:2014 | 09 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,951 | $7,604 | Implemented |
NC0518 # 08 Y:2014 | 08 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $2,258 | $4,256 | Implemented |
NC0518 # 11 Y:2014 | 11 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $536 | $160 | Implemented |
NC0518 # 10 Y:2014 | 10 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,688 | $3,708 | Implemented |
NC0518 # 13 Y:2014 | 13 | 2014 | INSTALL OCCUPANCY SENSORS | $437 | $774 | Implemented |
NC0518 # 12 Y:2014 | 12 | 2014 | USE PHOTOCELL CONTROLS | $103 | $80 | Implemented |
NC0518 # 02 Y:2014 | 02 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,224 | $50 | Implemented |
DL0127 # 01 Y:2014 | 01 | 2014 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,800 | $100 | Implemented |
DL0127 # 09 Y:2014 | 09 | 2014 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,800 | $250 | Implemented |
DL0127 # 12 Y:2014 | 12 | 2014 | INSTALL OCCUPANCY SENSORS | $3,400 | $2,300 | Implemented |
MI0257 # 06 Y:2014 | 06 | 2014 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $5,027 | $80 | Implemented |
MI0257 # 05 Y:2014 | 05 | 2014 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $6,335 | $2,660 | Implemented |