Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,146
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0841 # 02 Y:2022 | 02 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,631 | $155,407 | Implemented |
MA0841 # 01 Y:2022 | 01 | 2022 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $11,138 | $8,830 | Implemented |
AS0521 # 06 Y:2022 | 06 | 2022 | USE OPTIMUM THICKNESS INSULATION | $13 | $109 | Implemented |
AS0521 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $191 | $514 | Implemented |
AS0521 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $835 | $814 | Implemented |
AS0521 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,344 | $6,500 | Implemented |
AS0521 # 01 Y:2022 | 01 | 2022 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $52,178 | $1,517 | Implemented |
MA0835 # 04 Y:2022 | 04 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $680 | $750 | Implemented |
MA0835 # 02 Y:2022 | 02 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,773 | $7,150 | Implemented |
MA0835 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,572 | $40,722 | Implemented |
MA0836 # 08 Y:2022 | 08 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,781 | $625 | Implemented |
MA0836 # 07 Y:2022 | 07 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,777 | $7,150 | Implemented |
MA0836 # 06 Y:2022 | 06 | 2022 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $7,372 | $500 | Implemented |
MA0836 # 05 Y:2022 | 05 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,531 | $1,500 | Implemented |
MA0836 # 03 Y:2022 | 03 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $9,895 | $23,950 | Implemented |
LS2215 # 01 Y:2022 | 01 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $50,000 | $0 | Implemented |
LS2215 # 02 Y:2022 | 02 | 2022 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $9,603 | $1,118 | Implemented |
LS2215 # 03 Y:2022 | 03 | 2022 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $72,450 | $2,400 | Implemented |
LS2215 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $631 | $75 | Implemented |
LS2215 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,461 | $270 | Implemented |
LS2215 # 06 Y:2022 | 06 | 2022 | INSTALL OCCUPANCY SENSORS | $247 | $100 | Implemented |
LS2215 # 07 Y:2022 | 07 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $49,680 | $58,020 | Implemented |
KS2201 # 09 Y:2022 | 09 | 2022 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $13,164 | $120 | Implemented |
KS2201 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,572 | $61,880 | Implemented |
KS2201 # 04 Y:2022 | 04 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $39,082 | $154,800 | Implemented |