Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,832
matching recommendationsSIC | 2051 | Bread, Cake, And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0590 # 01 Y:2023 | 01 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $101,164 | $60,322 | Not Implemented |
UF0590 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $90,544 | $67,849 | Implemented |
UF0590 # 03 Y:2023 | 03 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $16,705 | $11,574 | Implemented |
UF0590 # 04 Y:2023 | 04 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $31,115 | $12,420 | Implemented |
UF0590 # 05 Y:2023 | 05 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,955 | $25,440 | Implemented |
UF0590 # 06 Y:2023 | 06 | 2023 | INSTALL SUB-METERING EQUIPMENT | $10,106 | $11,100 | Implemented |
UF0590 # 07 Y:2023 | 07 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $3,034 | $528 | Implemented |
UF0590 # 08 Y:2023 | 08 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $79,607 | $10,000 | Implemented |
OR0768 # 03 Y:2023 | 03 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $11,178 | $5,693 | Implemented |
OR0768 # 02 Y:2023 | 02 | 2023 | USE AUTOMATIC FLOW CONTROL | $24,867 | $9,600 | Not Implemented |
OR0768 # 01 Y:2023 | 01 | 2023 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $18,535 | $8,125 | Implemented |
CC0012 # 07 Y:2022 | 07 | 2022 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $47,241 | $125,000 | n/a |
CC0012 # 01 Y:2022 | 01 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $38,944 | $0 | n/a |
CC0012 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $18,525 | $10,000 | n/a |
CC0012 # 03 Y:2022 | 03 | 2022 | OPERATE BOILERS ON HIGH FIRE SETTING | $4,544 | $10,000 | n/a |
CC0012 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,343 | $16,000 | n/a |
CC0012 # 05 Y:2022 | 05 | 2022 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $3,233 | $0 | n/a |
CC0012 # 06 Y:2022 | 06 | 2022 | REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE | $7,230 | $30,000 | n/a |
UA0267 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $13,660 | $51,749 | Not Implemented |
UA0267 # 05 Y:2022 | 05 | 2022 | INSTALL OCCUPANCY SENSORS | $677 | $901 | Implemented |
UA0267 # 04 Y:2022 | 04 | 2022 | OPTIMIZE PLANT POWER FACTOR | $2,388 | $1,682 | Not Implemented |
UA0267 # 03 Y:2022 | 03 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $2,954 | $1,360 | Implemented |
UA0267 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,033 | $1,000 | Implemented |
UA0266 # 06 Y:2022 | 06 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $894 | $558 | Not Implemented |
UA0266 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,871 | $22,132 | Not Implemented |