Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
76
matching recommendationsSIC | 208 | Beverages |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0601 # 03 Y:2020 | 03 | 2020 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,944 | $3,000 | Implemented |
WV0601 # 04 Y:2020 | 04 | 2020 | INSTALL ISOLATION TRANSFORMER ON ADJUSTABLE FREQUENCY DRIVE | $4,392 | $6,660 | Implemented |
WV0601 # 05 Y:2020 | 05 | 2020 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,885 | $13,900 | Implemented |
WV0601 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,355 | $1,691 | Implemented |
UA0233 # 04 Y:2020 | 04 | 2020 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,500 | $20 | Implemented |
UA0233 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $260 | $1,068 | Implemented |
UA0233 # 02 Y:2020 | 02 | 2020 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $848 | $50 | Implemented |
UA0233 # 05 Y:2020 | 05 | 2020 | INSTALL OCCUPANCY SENSORS | $658 | $185 | Implemented |
UK2004 # 06 Y:2020 | 06 | 2020 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $71,487 | $150,900 | Implemented |
UK2004 # 05 Y:2020 | 05 | 2020 | INSULATE BARE EQUIPMENT | $52,668 | $24,890 | Implemented |
UK2004 # 04 Y:2020 | 04 | 2020 | INCREASE AMOUNT OF CONDENSATE RETURNED | $360,000 | $250,000 | Implemented |
UK2004 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,067 | $2,630 | Implemented |
UK2004 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,779 | $0 | Implemented |
UK2004 # 01 Y:2020 | 01 | 2020 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $6,031 | $21,360 | Implemented |
UK2004 # 07 Y:2020 | 07 | 2020 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $102,672 | $4,000 | Implemented |
UK2004 # 09 Y:2020 | 09 | 2020 | OPTIMIZE PLANT POWER FACTOR | $40,258 | $23,660 | Implemented |
UK2003 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $4,628 | $1,586 | Implemented |
UK2003 # 07 Y:2020 | 07 | 2020 | MINIMIZE WATER USAGE | $27,840 | $15,000 | Implemented |
UK2003 # 05 Y:2020 | 05 | 2020 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $15,645 | $28,100 | Implemented |
UF0550 # 02 Y:2020 | 02 | 2020 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $11,802 | $30,000 | Implemented |
UF0550 # 01 Y:2020 | 01 | 2020 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $41,888 | $29,990 | Implemented |
UF0550 # 04 Y:2020 | 04 | 2020 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,928 | $2,800 | Implemented |
UF0550 # 05 Y:2020 | 05 | 2020 | MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE | $383,788 | $897,972 | Implemented |
UF0550 # 03 Y:2020 | 03 | 2020 | INSTALL TURBULATORS | $3,921 | $11,250 | Implemented |
SF0550 # 05 Y:2020 | 05 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,560 | $12,365 | Implemented |