Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
280
matching recommendationsSIC | 22 | Textile Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0889 # 05 Y:2012 | 05 | 2012 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $24,926 | $6,000 | Not Implemented |
GT0889 # 03 Y:2012 | 03 | 2012 | INSULATE BARE EQUIPMENT | $4,743 | $3,920 | Not Implemented |
GT0889 # 02 Y:2012 | 02 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $14,795 | $8,500 | Not Implemented |
GT0889 # 01 Y:2012 | 01 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,925 | $1,000 | Not Implemented |
GT0796 # 08 Y:2004 | 08 | 2004 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $792 | $1,910 | Not Implemented |
GT0796 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,051 | $50,551 | Implemented |
GT0796 # 01 Y:2004 | 01 | 2004 | COMBINE UTILITY METERS | $4,508 | $9,000 | Not Implemented |
GT0796 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $895 | $200 | Implemented |
GT0796 # 03 Y:2004 | 03 | 2004 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $835 | $0 | Implemented |
GT0796 # 04 Y:2004 | 04 | 2004 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $815 | $500 | Not Implemented |
GT0796 # 05 Y:2004 | 05 | 2004 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $8,427 | $1,750 | Not Implemented |
GT0796 # 06 Y:2004 | 06 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,639 | $9,925 | Not Implemented |
GT0795 # 05 Y:2004 | 05 | 2004 | METER WASTE WATER | $7,272 | $0 | Not Implemented |
GT0795 # 04 Y:2004 | 04 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $12,828 | $48,861 | Not Implemented |
GT0795 # 01 Y:2004 | 01 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $43,709 | $0 | Not Implemented |
GT0795 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $42,201 | $34,000 | Not Implemented |
GT0795 # 03 Y:2004 | 03 | 2004 | USE SYNTHETIC LUBRICANT | $30,353 | $0 | Not Implemented |
GT0795 # 09 Y:2004 | 09 | 2004 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $18,125 | $6,300 | Not Implemented |
GT0795 # 10 Y:2004 | 10 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,570 | $2,910 | Not Implemented |
GT0795 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,890 | $836 | Not Implemented |
GT0795 # 08 Y:2004 | 08 | 2004 | DISCONNECT BALLASTS | $1,696 | $3,640 | Not Implemented |
GT0795 # 07 Y:2004 | 07 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $5,380 | $4,000 | Not Implemented |
NC0282 # 03 Y:2004 | 03 | 2004 | ADJUST BURNERS FOR EFFICIENT OPERATION | $7,098 | $1,000 | n/a |
NC0282 # 02 Y:2004 | 02 | 2004 | REDESIGN PROCESS | $5,960 | $6,000 | n/a |
NC0282 # 01 Y:2004 | 01 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $99,451 | $151,800 | n/a |