Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
79
matching recommendationsSIC | 2253 | Knit Outerwear Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0792 # 01 Y:2004 | 01 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $21,335 | $10,000 | Implemented |
NC0209 # 01 Y:2001 | 01 | 2001 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,845 | $5,600 | Not Implemented |
NC0209 # 05 Y:2001 | 05 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,886 | $2,360 | Implemented |
NC0209 # 02 Y:2001 | 02 | 2001 | UPGRADE CONTROLS ON COMPRESSORS | $2,519 | $5,600 | Implemented |
NC0209 # 03 Y:2001 | 03 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,161 | $5,700 | Not Implemented |
NC0209 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $163 | $200 | Implemented |
NC0209 # 06 Y:2001 | 06 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $675 | $200 | Not Implemented |
NC0203 # 08 Y:2000 | 08 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,141 | $6,000 | Not Implemented |
NC0203 # 07 Y:2000 | 07 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,732 | $849 | Not Implemented |
NC0203 # 01 Y:2000 | 01 | 2000 | MAINTAIN CLEAN CONDITIONS BEFORE PAINTING | $5,811 | $13,000 | Implemented |
NC0203 # 02 Y:2000 | 02 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,627 | $0 | Implemented |
NC0203 # 03 Y:2000 | 03 | 2000 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $24,784 | $8,500 | Not Implemented |
NC0203 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,597 | $150 | Implemented |
NC0203 # 05 Y:2000 | 05 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $630 | $691 | Implemented |
NC0203 # 06 Y:2000 | 06 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,299 | $220 | Not Implemented |
WI0349 # 01 Y:1999 | 01 | 1999 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $7,513 | $500 | Not Implemented |
WI0349 # 03 Y:1999 | 03 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $2,784 | $800 | Implemented |
WI0349 # 02 Y:1999 | 02 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,254 | $25,528 | Not Implemented |
WI0349 # 07 Y:1999 | 07 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,649 | $0 | Implemented |
WI0349 # 05 Y:1999 | 05 | 1999 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,927 | $500 | Implemented |
WI0349 # 09 Y:1999 | 09 | 1999 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $341 | $682 | Not Implemented |
WI0349 # 04 Y:1999 | 04 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,309 | $306 | Not Implemented |
WI0349 # 06 Y:1999 | 06 | 1999 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,918 | $0 | Not Implemented |
WI0349 # 08 Y:1999 | 08 | 1999 | COMBINE UTILITY METERS | $356 | $200 | Not Implemented |
UF0096 # 08 Y:1994 | 08 | 1994 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $17,977 | $19,000 | Not Implemented |