Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,223
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0109 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,030 | $20,000 | Implemented |
TT0109 # 06 Y:2013 | 06 | 2013 | APPLY FOR INVESTMENT INCENTIVES | $2,271 | $0 | Implemented |
TT0111 # 01 Y:2013 | 01 | 2013 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $6,000 | $5,000 | Not Implemented |
TT0111 # 02 Y:2013 | 02 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $17,000 | $50,000 | Not Implemented |
TT0111 # 03 Y:2013 | 03 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,000 | $5,000 | Implemented |
TT0111 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,000 | $4,000 | Implemented |
TT0111 # 05 Y:2013 | 05 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,000 | $1,500 | Implemented |
CO0671 # 01 Y:2013 | 01 | 2013 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $62,960 | $65,530 | Implemented |
CO0671 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $850 | $2,190 | Not Implemented |
OR0607 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $52,535 | $27,268 | Not Implemented |
OR0607 # 02 Y:2013 | 02 | 2013 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $4,626 | $5,352 | Not Implemented |
OR0607 # 03 Y:2013 | 03 | 2013 | OPTIMIZE PLANT POWER FACTOR | $3,603 | $9,150 | Not Implemented |
OR0607 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,983 | $7,504 | Implemented |
OR0607 # 05 Y:2013 | 05 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,021 | $5,130 | Implemented |
OR0602 # 01 Y:2013 | 01 | 2013 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $199,441 | $59,312 | Implemented |
OR0602 # 02 Y:2013 | 02 | 2013 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $17,131 | $45,000 | Not Implemented |
OR0602 # 03 Y:2013 | 03 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $14,855 | $19,467 | Implemented |
OR0602 # 04 Y:2013 | 04 | 2013 | INSTALL OCCUPANCY SENSORS | $5,434 | $10,283 | Implemented |
OR0602 # 05 Y:2013 | 05 | 2013 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $4,904 | $4,472 | Not Implemented |
OR0602 # 06 Y:2013 | 06 | 2013 | OPTIMIZE PLANT POWER FACTOR | $3,822 | $9,150 | Implemented |
OR0602 # 07 Y:2013 | 07 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,173 | $2,020 | Not Implemented |
OR0602 # 08 Y:2013 | 08 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,435 | $3,004 | Implemented |
NC0478 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,457 | $15,267 | Not Implemented |
NC0478 # 02 Y:2013 | 02 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $858 | $2,621 | Not Implemented |
NC0478 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $649 | $562 | Not Implemented |