Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
126
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0416 # 03 Y:2008 | 03 | 2008 | INSTALL TIMERS AND/OR THERMOSTATS | $53,629 | $49,236 | Not Implemented |
UF0416 # 07 Y:2008 | 07 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,708 | $1,477 | Implemented |
UF0416 # 01 Y:2008 | 01 | 2008 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $950 | $4,000 | Implemented |
UF0416 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $39,189 | $227,490 | Not Implemented |
OR0537 # 07 Y:2008 | 07 | 2008 | USE OPTIMUM THICKNESS INSULATION | $11,928 | $5,611 | Not Implemented |
OR0537 # 05 Y:2008 | 05 | 2008 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $4,386 | $18,550 | Not Implemented |
OR0537 # 04 Y:2008 | 04 | 2008 | INSTALL OCCUPANCY SENSORS | $10,283 | $27,375 | Not Implemented |
OR0537 # 08 Y:2008 | 08 | 2008 | $179,500 | $279,600 | Not Implemented | |
OR0537 # 01 Y:2008 | 01 | 2008 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $34,473 | $24,900 | Not Implemented |
OR0537 # 02 Y:2008 | 02 | 2008 | $56,459 | $10,000 | Not Implemented | |
OR0537 # 06 Y:2008 | 06 | 2008 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,113 | $0 | Implemented |
OR0537 # 03 Y:2008 | 03 | 2008 | REDUCE SCRAP PRODUCTION | $131,635 | $140,000 | Not Implemented |
OR0533 # 01 Y:2008 | 01 | 2008 | REDUCE SCRAP PRODUCTION | $34,537 | $0 | Implemented |
OR0533 # 02 Y:2008 | 02 | 2008 | USE SOLAR HEAT TO MAKE ELECTRICTY | $19,500 | $157,850 | Not Implemented |
OR0533 # 03 Y:2008 | 03 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,560 | $3,680 | Not Implemented |
OR0533 # 04 Y:2008 | 04 | 2008 | INSTALL OCCUPANCY SENSORS | $7,000 | $44,710 | Not Implemented |
OR0533 # 05 Y:2008 | 05 | 2008 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $8,300 | $2,500 | Implemented |
OR0533 # 06 Y:2008 | 06 | 2008 | OPTIMIZE PLANT POWER FACTOR | $3,400 | $5,075 | Not Implemented |
UM0340 # 04 Y:2008 | 04 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $329 | $500 | Implemented |
UM0340 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $490 | $447 | Not Implemented |
UM0340 # 03 Y:2008 | 03 | 2008 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $439 | $250 | Not Implemented |
UM0340 # 01 Y:2008 | 01 | 2008 | OPTIMIZE PLANT POWER FACTOR | $15,424 | $32,000 | Implemented |
WV0381 # 06 Y:2008 | 06 | 2008 | OPTIMIZE PLANT POWER FACTOR | $25,696 | $34,550 | Implemented |
WV0381 # 08 Y:2008 | 08 | 2008 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $21,259 | $25,425 | Implemented |
WV0381 # 07 Y:2008 | 07 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $25,395 | $2,100 | Implemented |