IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

138

matching recommendations
Reset
SIC 2493 Reconstituted Wood Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0718 # 03 Y:2019 03 2019 VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE $7,386 $27,337 Not Implemented
OR0718 # 02 Y:2019 02 2019 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $47,893 $5,142 Not Implemented
OR0718 # 01 Y:2019 01 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $84,306 $71,155 Not Implemented
OR0679 # 06 Y:2016 06 2016 REPLACE BOILER $48,912 $250,000 Not Implemented
OR0679 # 05 Y:2016 05 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,613 $47,385 Implemented
OR0679 # 04 Y:2016 04 2016 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $31,513 $47,575 Implemented
OR0679 # 03 Y:2016 03 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,003 $10,369 Not Implemented
OR0679 # 02 Y:2016 02 2016 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $20,472 $0 Implemented
OR0679 # 01 Y:2016 01 2016 TURN OFF EQUIPMENT WHEN NOT IN USE $74,285 $6,200 Implemented
OR0664 # 04 Y:2016 04 2016 UPGRADE CONVEYORS $74,609 $242,718 Not Implemented
OR0664 # 03 Y:2016 03 2016 INSTALL SPECTRAL REFLECTORS / DELAMP $12,507 $32,393 Implemented
OR0664 # 02 Y:2016 02 2016 INSULATE BARE EQUIPMENT $1,310 $2,584 Not Implemented
OR0664 # 01 Y:2016 01 2016 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $2,739 $0 Not Implemented
OR0657 # 03 Y:2015 03 2015 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $207,496 $694,826 Not Implemented
OR0657 # 02 Y:2015 02 2015 INSULATE BARE EQUIPMENT $24,174 $32,596 Not Implemented
OR0657 # 01 Y:2015 01 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $48,205 $50,205 Implemented
OR0640 # 05 Y:2014 05 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $11,092 $12,092 Implemented
OR0640 # 01 Y:2014 01 2014 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $131,605 $242,261 Implemented
OR0640 # 02 Y:2014 02 2014 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $2,455 $0 Not Implemented
OR0640 # 04 Y:2014 04 2014 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL $20,241 $67,550 Not Implemented
OR0640 # 03 Y:2014 03 2014 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $1,298 $1,020 Not Implemented
OR0622 # 02 Y:2013 02 2013 UPGRADE CONTROLS ON COMPRESSORS $10,631 $10,763 Not Implemented
OR0622 # 01 Y:2013 01 2013 IMPROVE COMBUSTION CONTROL CAPABILITY $9,626 $1,814 Not Implemented
OR0622 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,279 $15,410 Not Implemented
OR0622 # 03 Y:2013 03 2013 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $8,423 $20,917 Not Implemented