Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
546
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0498 # 03 Y:2015 | 03 | 2015 | REDUCE EXCESS STEAM BLEEDING | $10,701 | $14,842 | Not Implemented |
SD0498 # 02 Y:2015 | 02 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $14,048 | $21,000 | Not Implemented |
SD0498 # 01 Y:2015 | 01 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $14,239 | $1,000 | Implemented |
SF0463 # 01 Y:2015 | 01 | 2015 | USE POWER DURING OFF-PEAK PERIODS | $3,922 | $0 | Not Implemented |
SF0463 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,820 | $110 | Implemented |
SF0463 # 03 Y:2015 | 03 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,452 | $0 | Implemented |
SF0463 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $366 | $0 | Implemented |
SF0463 # 05 Y:2015 | 05 | 2015 | INSULATE BARE EQUIPMENT | $3,340 | $721 | Implemented |
SF0463 # 15 Y:2015 | 15 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,394 | $16,788 | Implemented |
SF0463 # 14 Y:2015 | 14 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,312 | $26,140 | Not Implemented |
SF0463 # 13 Y:2015 | 13 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $229 | $694 | Not Implemented |
SF0463 # 12 Y:2015 | 12 | 2015 | INSTALL OCCUPANCY SENSORS | $364 | $799 | Not Implemented |
SF0463 # 11 Y:2015 | 11 | 2015 | INSULATE FEEDWATER TANK | $490 | $993 | Implemented |
SF0463 # 10 Y:2015 | 10 | 2015 | USE PHOTOCELL CONTROLS | $1,236 | $2,331 | Not Implemented |
SF0463 # 09 Y:2015 | 09 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,990 | $2,660 | Implemented |
SF0463 # 06 Y:2015 | 06 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $28,979 | $14,516 | Implemented |
SF0463 # 07 Y:2015 | 07 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,451 | $2,500 | Not Implemented |
SF0463 # 08 Y:2015 | 08 | 2015 | REPAIR OR REPLACE STEAM TRAPS | $7,199 | $7,920 | Implemented |
SD0496 # 06 Y:2015 | 06 | 2015 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $869 | $1,356 | Implemented |
SD0496 # 05 Y:2015 | 05 | 2015 | USE PHOTOCELL CONTROLS | $2,674 | $2,420 | Implemented |
SD0496 # 04 Y:2015 | 04 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,546 | $18,500 | Not Implemented |
SD0496 # 03 Y:2015 | 03 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,239 | $7,006 | Implemented |
SD0496 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $10,851 | $12,449 | Implemented |
SD0496 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $43,186 | $113,400 | Implemented |
SD0495 # 05 Y:2015 | 05 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,299 | $10,489 | Not Implemented |