Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
18
matching recommendationsSIC | 267 | Misc. Converted Paper Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0340 # 05 Y:2002 | 05 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $155 | $20 | Implemented |
AS0340 # 11 Y:2002 | 11 | 2002 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $25,624 | $4,800 | Implemented |
AS0340 # 13 Y:2002 | 13 | 2002 | CLEAR AND RENT EXISTING SPACE | $60,660 | $8,804 | Implemented |
AS0340 # 01 Y:2002 | 01 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,113 | $5,518 | Implemented |
NV0133 # 06 Y:1999 | 06 | 1999 | PAY UTILITY BILLS ON TIME | $1,013 | $0 | Implemented |
NV0133 # 01 Y:1999 | 01 | 1999 | REPLACE BOILER | $20,745 | $14,694 | Implemented |
NV0066 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $90 | $31 | Implemented |
NV0066 # 02 Y:1996 | 02 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,307 | $270 | Implemented |
NV0066 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,462 | $200 | Implemented |
NV0066 # 05 Y:1996 | 05 | 1996 | INSTALL OCCUPANCY SENSORS | $245 | $94 | Implemented |
NV0066 # 07 Y:1996 | 07 | 1996 | HEAT WATER WITH EXHAUST HEAT | $5,214 | $3,300 | Implemented |
NV0066 # 08 Y:1996 | 08 | 1996 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $3,100 | $0 | Implemented |
NV0010 # 03 Y:1994 | 03 | 1994 | ADJUST BURNERS FOR EFFICIENT OPERATION | $4,473 | $400 | Implemented |
NV0010 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $521 | $120 | Implemented |
NV0010 # 05 Y:1994 | 05 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $136 | $200 | Implemented |
NV0010 # 07 Y:1994 | 07 | 1994 | INSULATE BARE EQUIPMENT | $181 | $138 | Implemented |
NV0010 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,150 | $1,950 | Implemented |
NV0010 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,502 | $482 | Implemented |