Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
113
matching recommendationsSIC | 267 | Misc. Converted Paper Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0341 # 04 Y:2006 | 04 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $1,455 | $929 | Not Implemented |
NC0341 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $353 | $100 | Implemented |
NC0341 # 06 Y:2006 | 06 | 2006 | DEVELOP STANDARD OPERATING PROCEDURES | $55,756 | $2,540 | Not Implemented |
NC0197 # 01 Y:2000 | 01 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $29,525 | $15,500 | Not Implemented |
NC0197 # 02 Y:2000 | 02 | 2000 | AVOID REWINDING MOTORS MORE THAN TWICE | $722 | $1,569 | Implemented |
NC0197 # 03 Y:2000 | 03 | 2000 | INSTALL TIMERS AND/OR THERMOSTATS | $1,176 | $1,200 | Not Implemented |
NC0197 # 04 Y:2000 | 04 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,310 | $2,478 | Implemented |
NC0197 # 05 Y:2000 | 05 | 2000 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $8,100 | $1,000 | Not Implemented |
NC0197 # 06 Y:2000 | 06 | 2000 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $1,596 | $3,500 | Not Implemented |
NC0197 # 07 Y:2000 | 07 | 2000 | ADOPT IN-HOUSE MATERIAL GENERATION | $97,778 | $1,000 | Implemented |
NC0192 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,843 | $10,160 | Not Implemented |
NC0192 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,718 | $50,100 | Not Implemented |
NC0192 # 03 Y:2000 | 03 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,432 | $3,250 | Implemented |
NC0192 # 04 Y:2000 | 04 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $87,421 | $288,000 | Not Implemented |
NC0192 # 05 Y:2000 | 05 | 2000 | USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING | $20,845 | $10,000 | Not Implemented |
TN0351 # 01 Y:1988 | 01 | 1988 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $106,613 | $25,500 | Implemented |
TN0351 # 03 Y:1988 | 03 | 1988 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,397 | $14,940 | Implemented |
TN0351 # 04 Y:1988 | 04 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,130 | $3,800 | Implemented |
TN0351 # 05 Y:1988 | 05 | 1988 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,132 | $1,055 | Not Implemented |
TN0351 # 06 Y:1988 | 06 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,880 | $1,800 | Implemented |
TN0351 # 07 Y:1988 | 07 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $289 | $30 | Implemented |
AT0051 # 01 Y:1986 | 01 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $263 | $400 | Implemented |
AT0051 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $50 | $55 | Implemented |
AT0051 # 03 Y:1986 | 03 | 1986 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $6,951 | $2,100 | Implemented |
AT0051 # 04 Y:1986 | 04 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $280 | $0 | Implemented |