Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
520
matching recommendationsSIC | 2679 | Converted Paper Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0207 # 02 Y:2005 | 02 | 2005 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,133 | $0 | Not Implemented |
SU0207 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,791 | $477 | Implemented |
SU0207 # 04 Y:2005 | 04 | 2005 | USE SYNTHETIC LUBRICANT | $2,489 | $2,000 | Not Implemented |
SU0207 # 05 Y:2005 | 05 | 2005 | ADJUST VENTS TO MINIMIZE ENERGY USE | $21,600 | $21,422 | Not Implemented |
SU0207 # 06 Y:2005 | 06 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $55 | $92 | Implemented |
WV0294 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30,792 | $30,627 | Not Implemented |
WV0294 # 02 Y:2004 | 02 | 2004 | INSTALL OCCUPANCY SENSORS | $10,219 | $4,900 | Not Implemented |
WV0294 # 03 Y:2004 | 03 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $5,704 | $230 | Implemented |
WV0294 # 04 Y:2004 | 04 | 2004 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $4,247 | $2,660 | Implemented |
WV0294 # 05 Y:2004 | 05 | 2004 | EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | $509,116 | $20,000 | Not Implemented |
WV0294 # 06 Y:2004 | 06 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,472 | $920 | Implemented |
WV0294 # 07 Y:2004 | 07 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,431 | $784 | Implemented |
WV0294 # 08 Y:2004 | 08 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,317 | $215 | Implemented |
WV0294 # 09 Y:2004 | 09 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $609 | $46 | Implemented |
WV0294 # 10 Y:2004 | 10 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $232 | $129 | Not Implemented |
LM0076 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $528 | $25 | Implemented |
LM0076 # 02 Y:2004 | 02 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,952 | $1,300 | Implemented |
LM0076 # 03 Y:2004 | 03 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $255 | $281 | Implemented |
LM0076 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,953 | $3,825 | Not Implemented |
LM0076 # 05 Y:2004 | 05 | 2004 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $6,736 | $2,500 | Implemented |
LM0076 # 06 Y:2004 | 06 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,766 | $1,500 | Not Implemented |
LM0076 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,513 | $880 | Implemented |
MS0220 # 01 Y:2003 | 01 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $118,492 | $100 | Implemented |
MS0220 # 02 Y:2003 | 02 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $12,922 | $2,070 | Not Implemented |
MS0220 # 03 Y:2003 | 03 | 2003 | USE RADIANT HEATER FOR SPOT HEATING | $2,495 | $600 | Not Implemented |