IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,451

matching recommendations
Reset
SIC 275 Commercial Printing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0518 # 03 Y:2006 03 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,873 $0 Implemented
WI0518 # 07 Y:2006 07 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,994 $2,560 Implemented
WI0518 # 08 Y:2006 08 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,722 $0 Implemented
WI0518 # 09 Y:2006 09 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,210 $778 Implemented
IA0387 # 02 Y:2006 02 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,927 $15,519 Implemented
IA0387 # 05 Y:2006 05 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,935 $50 Implemented
IA0387 # 06 Y:2006 06 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,664 $500 Implemented
WV0335 # 02 Y:2006 02 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $127,911 $14,450 Implemented
WV0335 # 04 Y:2006 04 2006 DEVELOP A REPAIR/REPLACE POLICY $6,057 $240 Implemented
WV0335 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,865 $1,420 Implemented
WV0335 # 06 Y:2006 06 2006 UTILIZE A LESS EXPENSIVE COOLING METHOD $2,785 $5,803 Implemented
WV0335 # 08 Y:2006 08 2006 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $985 $1,680 Implemented
MA0598 # 02 Y:2006 02 2006 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $19,748 $1,125 Implemented
MA0598 # 03 Y:2006 03 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,315 $18,065 Implemented
MA0598 # 04 Y:2006 04 2006 INSULATE BARE EQUIPMENT $4,500 $4,314 Implemented
MA0598 # 07 Y:2006 07 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $405 $300 Implemented
LM0107 # 02 Y:2006 02 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,219 $2,200 Implemented
LM0107 # 03 Y:2006 03 2006 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $225,208 $12,980 Implemented
LM0107 # 04 Y:2006 04 2006 DEVELOP STANDARD OPERATING PROCEDURES $178,334 $5,400 Implemented
LM0107 # 05 Y:2006 05 2006 ADOPT IN-HOUSE MATERIAL GENERATION $16,864 $1,000 Implemented
LM0107 # 06 Y:2006 06 2006 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $20,251 $1,000 Implemented
UD0731 # 01 Y:2005 01 2005 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES $54,200 $60,000 Implemented
UD0731 # 07 Y:2005 07 2005 CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES $12,378 $0 Implemented
UD0731 # 09 Y:2005 09 2005 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $6,841 $0 Implemented
UD0731 # 10 Y:2005 10 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,953 $15,113 Implemented