Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,057
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0807 # 03 Y:2025 | 03 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $753 | $2,323 | n/a |
OR0807 # 01 Y:2025 | 01 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,168 | $10,530 | n/a |
OR0807 # 04 Y:2025 | 04 | 2025 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $3,635 | $16,079 | n/a |
OR0807 # 02 Y:2025 | 02 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,721 | $7,534 | n/a |
UL2507 # 03 Y:2025 | 03 | 2025 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $16,032 | $37,000 | n/a |
UL2507 # 02 Y:2025 | 02 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,632 | $24,675 | n/a |
UL2507 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $56,773 | $527,158 | n/a |
UF0632 # 13 Y:2025 | 13 | 2025 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,094 | $0 | n/a |
UF0632 # 09 Y:2025 | 09 | 2025 | INSTALL TURBULATORS | $2,277 | $3,750 | n/a |
UF0632 # 07 Y:2025 | 07 | 2025 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $4,170 | $6,785 | n/a |
UF0632 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,631 | $322,608 | n/a |
UF0632 # 03 Y:2025 | 03 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,911 | $34,076 | n/a |
UF0632 # 11 Y:2025 | 11 | 2025 | USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL | $3,839 | $3,079 | n/a |
UF0632 # 04 Y:2025 | 04 | 2025 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,726 | $12,000 | n/a |
UF0632 # 12 Y:2025 | 12 | 2025 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $7,429 | $20,000 | n/a |
UF0632 # 10 Y:2025 | 10 | 2025 | INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK | $2,684 | $2,743 | n/a |
UF0632 # 02 Y:2025 | 02 | 2025 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $21,772 | $20,202 | n/a |
UF0632 # 06 Y:2025 | 06 | 2025 | IMPROVE COMBUSTION CONTROL CAPABILITY | $4,200 | $2,000 | n/a |
UF0632 # 08 Y:2025 | 08 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,170 | $2,654 | n/a |
UF0632 # 05 Y:2025 | 05 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,526 | $20,560 | n/a |
UF0632 # 14 Y:2025 | 14 | 2025 | IMPROVE SPACE COMFORT CONDITIONING | $1,115 | $3,888 | n/a |
UL2506 # 01 Y:2025 | 01 | 2025 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $77,396 | $40,000 | n/a |
UL2506 # 04 Y:2025 | 04 | 2025 | OPTIMIZE PLANT POWER FACTOR | $49,775 | $25,480 | n/a |
UL2506 # 06 Y:2025 | 06 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,323 | $17,116 | n/a |
UL2506 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,455 | $2,940 | n/a |