Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NV0119 # 01 Y:1998 | 01 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $60,884 | $48,211 | Implemented |
NV0119 # 03 Y:1998 | 03 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,499 | $0 | Implemented |
NV0111 # 01 Y:1998 | 01 | 1998 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $12,730 | $690 | Implemented |
NV0111 # 02 Y:1998 | 02 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,601 | $1,601 | Implemented |
NV0111 # 07 Y:1998 | 07 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,329 | $607 | Implemented |
NV0091 # 01 Y:1997 | 01 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,073 | $245 | Implemented |
NV0091 # 03 Y:1997 | 03 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $6,435 | $380 | Implemented |
NV0091 # 04 Y:1997 | 04 | 1997 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,330 | $400 | Implemented |
NV0084 # 14 Y:1997 | 14 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $312 | $0 | Implemented |
NV0084 # 07 Y:1997 | 07 | 1997 | HEAT TREAT PARTS ONLY TO REQUIRED SPECIFICATIONS OR STANDARDS | $102 | $0 | Implemented |
NV0084 # 05 Y:1997 | 05 | 1997 | INSULATE BARE EQUIPMENT | $431 | $1,035 | Implemented |
NV0084 # 04 Y:1997 | 04 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $258 | $308 | Implemented |
NV0084 # 02 Y:1997 | 02 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,562 | $375 | Implemented |
NV0084 # 08 Y:1997 | 08 | 1997 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $450 | $690 | Implemented |
NV0084 # 12 Y:1997 | 12 | 1997 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $394 | $147 | Implemented |
NV0084 # 13 Y:1997 | 13 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $437 | $120 | Implemented |
NV0063 # 01 Y:1996 | 01 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,596 | $200 | Implemented |
NV0063 # 03 Y:1996 | 03 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,184 | $90 | Implemented |
NV0063 # 04 Y:1996 | 04 | 1996 | INSTALL OCCUPANCY SENSORS | $100 | $57 | Implemented |
NV0063 # 06 Y:1996 | 06 | 1996 | INSULATE BARE EQUIPMENT | $2,375 | $1,452 | Implemented |
NV0063 # 07 Y:1996 | 07 | 1996 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,535 | $5,200 | Implemented |
NV0063 # 08 Y:1996 | 08 | 1996 | USE OPTIMUM THICKNESS INSULATION | $9,970 | $2,000 | Implemented |
NV0063 # 09 Y:1996 | 09 | 1996 | USE OPTIMUM THICKNESS INSULATION | $4,848 | $6,210 | Implemented |
NV0063 # 11 Y:1996 | 11 | 1996 | MODIFY MATERIAL APPLICATION METHODS | $28,063 | $2,040 | Implemented |
NV0039 # 07 Y:1995 | 07 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $510 | $200 | Implemented |