Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
120
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0722 # 01 Y:2001 | 01 | 2001 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $16,455 | $5,110 | Implemented |
GT0722 # 05 Y:2001 | 05 | 2001 | INSULATE FEEDWATER TANK | $153 | $220 | Implemented |
GT0722 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $851 | $2,902 | Implemented |
AM0403 # 05 Y:2001 | 05 | 2001 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $10,730 | $0 | Implemented |
AM0403 # 12 Y:2001 | 12 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $380 | $0 | Implemented |
AM0403 # 11 Y:2001 | 11 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $900 | $0 | Implemented |
AM0403 # 10 Y:2001 | 10 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,400 | $0 | Implemented |
AM0403 # 09 Y:2001 | 09 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,380 | $2,640 | Implemented |
AM0403 # 07 Y:2001 | 07 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,050 | $5,890 | Implemented |
AM0403 # 06 Y:2001 | 06 | 2001 | INCREASE AMOUNT OF CONDENSATE RETURNED | $16,000 | $4,200 | Implemented |
AM0403 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $30,400 | $1,770 | Implemented |
IA0280 # 05 Y:2001 | 05 | 2001 | REPAIR OR REPLACE STEAM TRAPS | $87,600 | $7,916 | Implemented |
IA0280 # 06 Y:2001 | 06 | 2001 | REPAIR AND ELIMINATE STEAM LEAKS | $25,698 | $10,330 | Implemented |
SF0226 # 11 Y:2001 | 11 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $863 | $1,126 | Implemented |
SF0226 # 10 Y:2001 | 10 | 2001 | INSTALL OCCUPANCY SENSORS | $1,758 | $2,040 | Implemented |
SF0226 # 08 Y:2001 | 08 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,717 | $2,500 | Implemented |
SF0226 # 05 Y:2001 | 05 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $35,839 | $11,800 | Implemented |
SF0226 # 07 Y:2001 | 07 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,016 | $3,275 | Implemented |
SF0226 # 06 Y:2001 | 06 | 2001 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $844 | $535 | Implemented |
UU0011 # 03 Y:2001 | 03 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $24,413 | $85,168 | Implemented |
UU0011 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $745 | $140 | Implemented |
LL0122 # 04 Y:2001 | 04 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,898 | $660 | Implemented |
LL0122 # 05 Y:2001 | 05 | 2001 | USE PHOTOCELL CONTROLS | $8,786 | $495 | Implemented |
UU0011 # 02 Y:2001 | 02 | 2001 | USE SYNTHETIC LUBRICANT | $44,401 | $4,000 | Implemented |
UU0011 # 01 Y:2001 | 01 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $55,587 | $47,184 | Implemented |