Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
132
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0788 # 02 Y:2024 | 02 | 2024 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $25,469 | $59,617 | n/a |
OR0788 # 04 Y:2024 | 04 | 2024 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $6,183 | $10,497 | n/a |
OR0788 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,448 | $30,426 | n/a |
OR0788 # 05 Y:2024 | 05 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $3,766 | $18,699 | n/a |
OR0788 # 01 Y:2024 | 01 | 2024 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $126,866 | $607,450 | n/a |
OR0788 # 06 Y:2024 | 06 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $213 | $6,559 | n/a |
OR0779 # 01 Y:2023 | 01 | 2023 | ELIMINATE/REDUCE AN OPERATION | $3,315 | $0 | n/a |
OR0779 # 03 Y:2023 | 03 | 2023 | ADOPT IN-HOUSE MATERIAL GENERATION | $43,575 | $54,837 | n/a |
OR0779 # 02 Y:2023 | 02 | 2023 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,749 | $0 | n/a |
OR0779 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $4,725 | $57,101 | n/a |
OR0772 # 02 Y:2023 | 02 | 2023 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $9,363 | $1,352 | Not Implemented |
OR0772 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $1,740 | $3,039 | Implemented |
OR0772 # 06 Y:2023 | 06 | 2023 | INSULATE BARE EQUIPMENT | $1,312 | $5,390 | Implemented |
OR0772 # 04 Y:2023 | 04 | 2023 | OPTIMIZE PLANT POWER FACTOR | $5,801 | $7,178 | Not Implemented |
OR0772 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,514 | $8,385 | Implemented |
OR0772 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $22,304 | $25,167 | Not Implemented |
OR0706 # 03 Y:2018 | 03 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,311 | $2,097 | Not Implemented |
OR0706 # 01 Y:2018 | 01 | 2018 | REPAIR AND ELIMINATE STEAM LEAKS | $12,552 | $1,970 | Implemented |
OR0706 # 02 Y:2018 | 02 | 2018 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $15,952 | $28,542 | Not Implemented |
OR0706 # 04 Y:2018 | 04 | 2018 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $8,000 | $24,775 | Implemented |
OR0706 # 06 Y:2018 | 06 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $854 | $0 | Implemented |
OR0706 # 05 Y:2018 | 05 | 2018 | REDUCE FLUID FLOW RATES | $1,821 | $3,221 | Not Implemented |
OR0670 # 01 Y:2016 | 01 | 2016 | REDUCE FLUID FLOW RATES | $244,946 | $880,000 | Not Implemented |
OR0670 # 06 Y:2016 | 06 | 2016 | USE SOLAR HEAT TO MAKE ELECTRICTY | $29,141 | $269,109 | Not Implemented |
OR0670 # 05 Y:2016 | 05 | 2016 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $8,398 | $2,405 | Not Implemented |