matching recommendationsSIC | 2861 | Gum And Wood Chemicals |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0501 # 02 Y:2017 | 02 | 2017 | OPTIMIZE PLANT POWER FACTOR | $154,176 | $60,284 | Implemented |
UF0501 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $77,438 | $2,184 | Implemented |
UF0501 # 04 Y:2017 | 04 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $32,236 | $1,794 | Implemented |
UF0501 # 01 Y:2017 | 01 | 2017 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $1,393,980 | $3,306,000 | Not Implemented |
UF0501 # 05 Y:2017 | 05 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $29,058 | $39,050 | Implemented |
UF0501 # 06 Y:2017 | 06 | 2017 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $9,110 | $700 | Implemented |
UF0501 # 08 Y:2017 | 08 | 2017 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $5,834 | $0 | Implemented |
UF0501 # 09 Y:2017 | 09 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,020 | $482 | Implemented |
UF0501 # 07 Y:2017 | 07 | 2017 | USE OPTIMUM THICKNESS INSULATION | $6,596 | $11,216 | Implemented |
MS0326 # 02 Y:2008 | 02 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $48,711 | $29,850 | Not Implemented |
MS0326 # 04 Y:2008 | 04 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $14,110 | $500 | Implemented |
MS0326 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,624 | $376 | Implemented |
MS0326 # 01 Y:2008 | 01 | 2008 | REPAIR AND ELIMINATE STEAM LEAKS | $1,062,600 | $94 | Implemented |
OK0718 # 06 Y:2005 | 06 | 2005 | INSULATE BARE EQUIPMENT | $1,343 | $1,693 | Implemented |
OK0718 # 08 Y:2005 | 08 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,226 | $66,500 | Implemented |
OK0718 # 02 Y:2005 | 02 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,021 | $40,875 | Not Implemented |
OK0718 # 05 Y:2005 | 05 | 2005 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $2,243 | $5,175 | Not Implemented |
OK0718 # 07 Y:2005 | 07 | 2005 | USE OPTIMUM THICKNESS INSULATION | $2,162 | $1,710 | Implemented |
OK0718 # 03 Y:2005 | 03 | 2005 | USE COMPRESSOR AIR FILTERS | $5,034 | $459 | Not Implemented |
OK0718 # 04 Y:2005 | 04 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,239 | $8,030 | Not Implemented |
OK0718 # 01 Y:2005 | 01 | 2005 | DEVELOP A REPAIR/REPLACE POLICY | $12,970 | $500 | Implemented |
GT0590 # 08 Y:1996 | 08 | 1996 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $22,680 | $2,500 | Implemented |
GT0590 # 07 Y:1996 | 07 | 1996 | USE PHOTOCELL CONTROLS | $680 | $218 | Not Implemented |
GT0590 # 06 Y:1996 | 06 | 1996 | REDUCE EXCESSIVE BOILER BLOWDOWN | $18,987 | $400 | Implemented |
GT0590 # 05 Y:1996 | 05 | 1996 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $38,880 | $60,000 | Not Implemented |