Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
967
matching recommendationsSIC | 295 | Asphalt Paving And Roofing Materials |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0249 # 06 Y:2025 | 06 | 2025 | INSULATE BARE EQUIPMENT | $35,225 | $8,950 | n/a |
DL0249 # 05 Y:2025 | 05 | 2025 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,172 | $13,000 | n/a |
DL0249 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,102 | $10,000 | n/a |
DL0249 # 03 Y:2025 | 03 | 2025 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,075 | $1,777 | n/a |
DL0249 # 02 Y:2025 | 02 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,975 | $20,000 | n/a |
DL0249 # 01 Y:2025 | 01 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $43,100 | $30,000 | n/a |
IC0301 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,209 | $186,605 | Not Implemented |
IC0301 # 02 Y:2024 | 02 | 2024 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $26,388 | $3,600 | Implemented |
IC0301 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,886 | $205 | Implemented |
IC0301 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,652 | $0 | Implemented |
IC0301 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,042 | $205 | Implemented |
IC0301 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,487 | $0 | Implemented |
IC0301 # 07 Y:2024 | 07 | 2024 | USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING | $13,766 | $3,820 | Not Implemented |
IC0301 # 08 Y:2024 | 08 | 2024 | ELIMINATE COMBUSTIBLE GAS IN FLUE GAS | $2,673 | $890 | Not Implemented |
UF0605 # 06 Y:2023 | 06 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $5,654 | $20,000 | Implemented |
UF0605 # 05 Y:2023 | 05 | 2023 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,444,605 | $0 | Implemented |
UF0605 # 04 Y:2023 | 04 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $3,043 | $2,800 | Implemented |
UF0605 # 03 Y:2023 | 03 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,825 | $11,200 | Implemented |
UF0605 # 02 Y:2023 | 02 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $38,052 | $10,000 | Implemented |
UF0605 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $108,422 | $322,608 | Not Implemented |
UA0280 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,338 | $353 | Not Implemented |
UA0280 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,180 | $3,163 | Implemented |
UA0280 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,472 | $1,000 | Implemented |
UA0280 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,752 | $7,431 | Not Implemented |
UA0269 # 01 Y:2023 | 01 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $147,247 | $186,762 | Not Implemented |