Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
500
matching recommendationsSIC | 2952 | Asphalt Felts And Coatings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0263 # 07 Y:2007 | 07 | 2007 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,431 | $745 | Implemented |
LL0263 # 08 Y:2007 | 08 | 2007 | INSTALL OCCUPANCY SENSORS | $2,145 | $660 | Not Implemented |
LL0263 # 09 Y:2007 | 09 | 2007 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $338 | $390 | Not Implemented |
LL0263 # 10 Y:2007 | 10 | 2007 | INSTALL TIMERS AND/OR THERMOSTATS | $266 | $360 | Not Implemented |
LM0111 # 01 Y:2006 | 01 | 2006 | USE OPTIMUM TEMPERATURE | $1,018 | $0 | Not Implemented |
LM0111 # 02 Y:2006 | 02 | 2006 | INSULATE BARE EQUIPMENT | $2,109 | $3,000 | Implemented |
LM0111 # 03 Y:2006 | 03 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $879 | $5,000 | Implemented |
LM0111 # 04 Y:2006 | 04 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,249 | $522 | Not Implemented |
LM0111 # 05 Y:2006 | 05 | 2006 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $235,359 | $7,000 | Not Implemented |
LM0111 # 06 Y:2006 | 06 | 2006 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $650,132 | $0 | Implemented |
OK0719 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $56,779 | $157,975 | Not Implemented |
OK0719 # 02 Y:2006 | 02 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $13,491 | $550 | Implemented |
OK0719 # 03 Y:2006 | 03 | 2006 | USE OPTIMUM THICKNESS INSULATION | $3,078 | $1,637 | Implemented |
OK0719 # 04 Y:2006 | 04 | 2006 | INSULATE BARE EQUIPMENT | $249 | $1,098 | Not Implemented |
OK0719 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $282 | $80 | Implemented |
OK0719 # 06 Y:2006 | 06 | 2006 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $221 | $225 | Implemented |
OK0719 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $49 | $92 | Not Implemented |
CO0580 # 01 Y:2006 | 01 | 2006 | INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT | $479,740 | $28,080 | Not Implemented |
CO0580 # 02 Y:2006 | 02 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $10,650 | $500 | Implemented |
CO0580 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $9,880 | $3,190 | Not Implemented |
CO0580 # 04 Y:2006 | 04 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $3,750 | $12,850 | Implemented |
CO0580 # 05 Y:2006 | 05 | 2006 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $3,310 | $980 | Implemented |
CO0580 # 06 Y:2006 | 06 | 2006 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $1,460 | $9,360 | Not Implemented |
CO0580 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $50 | $20 | Implemented |
CO0580 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $900 | $1,610 | Not Implemented |