Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,293
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0203 # 01 Y:2024 | 01 | 2024 | USE AUTOMATIC FLOW CONTROL | $56,666 | $700 | n/a |
SJ0030 # 08 Y:2025 | 08 | 2025 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $663 | $4,755 | n/a |
SJ0030 # 07 Y:2025 | 07 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,287 | $0 | n/a |
SJ0030 # 06 Y:2025 | 06 | 2025 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $70,368 | $30,719 | n/a |
SJ0030 # 05 Y:2025 | 05 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $136 | $1,200 | n/a |
SJ0030 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,245 | $0 | n/a |
SJ0030 # 03 Y:2025 | 03 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,538 | $18,930 | n/a |
SJ0030 # 02 Y:2025 | 02 | 2025 | USE BATTERY STORAGE FOR DEMAND CONTROL | $18,627 | $195,217 | n/a |
SJ0030 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $630,866 | $6,247,450 | n/a |
GT0990 # 07 Y:2025 | 07 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $205,570 | $6,145,720 | n/a |
GT0990 # 06 Y:2025 | 06 | 2025 | OPTIMIZE PLANT POWER FACTOR | $2,014 | $8,907 | n/a |
GT0990 # 05 Y:2025 | 05 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,140 | $3,000 | n/a |
GT0990 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,284 | $19,750 | n/a |
GT0990 # 03 Y:2025 | 03 | 2025 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $313 | $200 | n/a |
GT0990 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,375 | $1,850 | n/a |
GT0990 # 01 Y:2025 | 01 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,523 | $800 | n/a |
MS0439 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $586 | $8,100 | n/a |
MS0439 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,650 | $0 | n/a |
MS0439 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $2,676 | $7,542 | n/a |
MS0439 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $121,416 | $769,370 | n/a |
MS0439 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $1,314 | $1,810 | n/a |
TT0325 # 01 Y:2025 | 01 | 2025 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $242,348 | $1,045,217 | n/a |
TT0325 # 02 Y:2025 | 02 | 2025 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $68,822 | $200,000 | n/a |
TT0325 # 03 Y:2025 | 03 | 2025 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $30,978 | $17,480 | n/a |
TT0325 # 04 Y:2025 | 04 | 2025 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $8,824 | $22,500 | n/a |