Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
576
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0103 # 07 Y:1998 | 07 | 1998 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $600 | $100 | Implemented |
BD0103 # 08 Y:1998 | 08 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $47,448 | $21,500 | Implemented |
BD0105 # 01 Y:1998 | 01 | 1998 | INSTALL OCCUPANCY SENSORS | $2,422 | $1,850 | Not Implemented |
BD0105 # 02 Y:1998 | 02 | 1998 | INSULATE BARE EQUIPMENT | $1,337 | $2,730 | Not Implemented |
BD0105 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $498 | $450 | Implemented |
BD0105 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $258 | $258 | Implemented |
BD0105 # 05 Y:1998 | 05 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $144 | $100 | Not Implemented |
BD0105 # 06 Y:1998 | 06 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $21,209 | $21,000 | Not Implemented |
BD0105 # 07 Y:1998 | 07 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $356 | $1,300 | Not Implemented |
BD0105 # 08 Y:1998 | 08 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $60,756 | $130,000 | Implemented |
BD0104 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $637 | $945 | Implemented |
BD0104 # 02 Y:1998 | 02 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $395 | $600 | Implemented |
BD0104 # 03 Y:1998 | 03 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $305 | $100 | Implemented |
BD0104 # 04 Y:1998 | 04 | 1998 | USE SYNTHETIC LUBRICANT | $191 | $150 | Implemented |
BD0104 # 05 Y:1998 | 05 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $4,287 | $1,525 | Implemented |
BD0104 # 06 Y:1998 | 06 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $3,425 | $400 | Implemented |
BD0104 # 07 Y:1998 | 07 | 1998 | MINIMIZE WATER USAGE | $823 | $1,125 | Implemented |
BD0104 # 08 Y:1998 | 08 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $3,375 | $4,395 | Implemented |
BD0101 # 01 Y:1998 | 01 | 1998 | INSTALL TURBULATORS | $28,680 | $1,650 | Implemented |
BD0101 # 02 Y:1998 | 02 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $26,005 | $40,190 | Implemented |
BD0101 # 03 Y:1998 | 03 | 1998 | INSTALL AUTOMATIC STACK DAMPER | $6,809 | $2,100 | Not Implemented |
BD0101 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,851 | $3,986 | Implemented |
BD0101 # 05 Y:1998 | 05 | 1998 | REPLACE WATER COOLING ON PROCESSES WITH AIR COOLING | $32,510 | $128,700 | Not Implemented |
BD0101 # 06 Y:1998 | 06 | 1998 | MINIMIZE WATER USAGE | $688 | $1,625 | Implemented |
BD0101 # 07 Y:1998 | 07 | 1998 | INSTALL AUTOMATIC PACKING EQUIPMENT | $133,152 | $72,000 | Not Implemented |