Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

387

matching recommendations
Reset
SIC 308 Miscellaneous Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0786 # 02 Y:2004 02 2004 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $33,950 $38,000 Not Implemented
GT0786 # 01 Y:2004 01 2004 MAINTAIN MACHINES TO REDUCE LEAKS $121,900 $45,000 Implemented
GT0763 # 11 Y:2003 11 2003 UTILIZE A LESS EXPENSIVE COOLING METHOD $8,026 $1,500 Not Implemented
GT0763 # 10 Y:2003 10 2003 CONTROL PRESSURE ON STEAMER OPERATIONS $11,010 $5,823 Not Implemented
GT0763 # 09 Y:2003 09 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $536 $5,146 Implemented
GT0763 # 08 Y:2003 08 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $2,503 $19,339 Implemented
GT0763 # 07 Y:2003 07 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,795 $12,447 Not Implemented
GT0763 # 06 Y:2003 06 2003 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,086 $7,250 Not Implemented
GT0763 # 05 Y:2003 05 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,266 $11,300 Not Implemented
GT0763 # 04 Y:2003 04 2003 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $81 $110 Implemented
GT0763 # 03 Y:2003 03 2003 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $696 $1,680 Not Implemented
GT0763 # 02 Y:2003 02 2003 KEEP EQUIPMENT CLEAN $655 $0 Implemented
GT0763 # 01 Y:2003 01 2003 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $8,000 $1,350 Implemented
GT0692 # 08 Y:2000 08 2000 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $5,155 $0 Not Implemented
GT0692 # 07 Y:2000 07 2000 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $19,321 $41,750 Not Implemented
GT0692 # 06 Y:2000 06 2000 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $9,831 $26,400 Not Implemented
GT0692 # 05 Y:2000 05 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $53,500 $170,000 Not Implemented
GT0692 # 04 Y:2000 04 2000 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $3,465 $500 Not Implemented
GT0692 # 03 Y:2000 03 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,690 $4,000 Implemented
GT0692 # 02 Y:2000 02 2000 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $7,810 $1,000 Implemented
GT0692 # 01 Y:2000 01 2000 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $7,357 $2,000 Implemented
GT0689 # 03 Y:2000 03 2000 INSTALL AUTOMATIC PACKING EQUIPMENT $72,000 $112,000 n/a
GT0689 # 01 Y:2000 01 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $32,450 $0 n/a
GT0689 # 02 Y:2000 02 2000 REPROCESS SPENT OILS ON SITE FOR RE-USE $9,458 $8,900 n/a
GT0689 # 04 Y:2000 04 2000 ADD ADDITIONAL PRODUCTION SHIFT $336,000 $225,000 n/a