Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
703
matching recommendationsSIC | 3084 | Plastics Pipe |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0418 # 12 Y:2008 | 12 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $729 | $0 | Implemented |
UF0418 # 11 Y:2008 | 11 | 2008 | INSTALL OCCUPANCY SENSORS | $5,889 | $6,806 | Implemented |
UF0418 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,945 | $34,619 | Not Implemented |
UF0418 # 09 Y:2008 | 09 | 2008 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,856 | $809 | Implemented |
UF0418 # 08 Y:2008 | 08 | 2008 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $39,146 | $1,589 | Implemented |
UF0418 # 05 Y:2008 | 05 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,900 | $800 | Implemented |
UF0418 # 07 Y:2008 | 07 | 2008 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $3,791 | $0 | Implemented |
LL0304 # 01 Y:2008 | 01 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $59,266 | $14,840 | Implemented |
LL0304 # 02 Y:2008 | 02 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $57,876 | $20,949 | Not Implemented |
LL0304 # 03 Y:2008 | 03 | 2008 | INSULATE BARE EQUIPMENT | $9,892 | $1,118 | Not Implemented |
LL0304 # 04 Y:2008 | 04 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,714 | $30 | Not Implemented |
LL0304 # 05 Y:2008 | 05 | 2008 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,456 | $825 | Not Implemented |
LL0304 # 06 Y:2008 | 06 | 2008 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $823 | $1,246 | Not Implemented |
LL0304 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $101 | $70 | Implemented |
MI0171 # 01 Y:2008 | 01 | 2008 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $170,598 | $351,000 | Not Implemented |
MI0171 # 02 Y:2008 | 02 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $131,514 | $7,800 | Not Implemented |
MI0171 # 03 Y:2008 | 03 | 2008 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $110,098 | $168,305 | Not Implemented |
MI0171 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $101,069 | $53,922 | Not Implemented |
MI0171 # 05 Y:2008 | 05 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $42,003 | $860 | Not Implemented |
MI0171 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,317 | $1,210 | Not Implemented |
OK0767 # 01 Y:2008 | 01 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $14,145 | $1,383 | Implemented |
OK0767 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,151 | $34,635 | Not Implemented |
OK0767 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $803 | $3,455 | Not Implemented |
OK0767 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,640 | $7,796 | Not Implemented |
OK0767 # 05 Y:2008 | 05 | 2008 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,068 | $200 | Implemented |