Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
60
matching recommendationsSIC | 3089 | Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1094 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $573 | $870 | Implemented |
OK1094 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,917 | $22,000 | Implemented |
OK1094 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,890 | $94,115 | Implemented |
OK0934 # 04 Y:2016 | 04 | 2016 | INSULATE BARE EQUIPMENT | $63,243 | $3,161 | Implemented |
OK0934 # 03 Y:2016 | 03 | 2016 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $134,039 | $1,300 | Implemented |
OK0908 # 01 Y:2015 | 01 | 2015 | OPTIMIZE PLANT POWER FACTOR | $6,429 | $11,430 | Implemented |
OK0908 # 03 Y:2015 | 03 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $621 | $432 | Implemented |
TT0090 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $134 | $525 | Implemented |
TT0090 # 08 Y:2012 | 08 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $2,350 | $2,400 | Implemented |
TT0090 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $1,008 | $1,780 | Implemented |
TT0090 # 04 Y:2012 | 04 | 2012 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,764 | $2,000 | Implemented |
TT0090 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $334 | $0 | Implemented |
TT0090 # 03 Y:2012 | 03 | 2012 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,275 | $1,000 | Implemented |
LL0266 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42,563 | $14,000 | Implemented |
LL0266 # 02 Y:2007 | 02 | 2007 | INSULATE BARE EQUIPMENT | $21,291 | $1,905 | Implemented |
AR0187 # 05 Y:2000 | 05 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $32 | $0 | Implemented |
AR0187 # 04 Y:2000 | 04 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $526 | $783 | Implemented |
AR0154 # 02 Y:1998 | 02 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $49,699 | $135,000 | Implemented |
AR0154 # 03 Y:1998 | 03 | 1998 | RECOVER AND REUSE COOLING WATER | $4,517 | $6,800 | Implemented |
AR0154 # 05 Y:1998 | 05 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $52,562 | $0 | Implemented |
AR0154 # 01 Y:1998 | 01 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $99 | $207 | Implemented |
AR0095 # 04 Y:1996 | 04 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,524 | $160 | Implemented |
AR0095 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,185 | $1,006 | Implemented |
AR0095 # 07 Y:1996 | 07 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,175 | $1,008 | Implemented |
AR0095 # 09 Y:1996 | 09 | 1996 | MAINTAIN MACHINES TO REDUCE LEAKS | $1,314 | $900 | Implemented |